2405 W IVANHOE DR 90039

Certificate Information: 2405 W IVANHOE DR 90039

Application / Permit
23047-10000-00077
Plan Check / Job No.
B23LA00581
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
1 OF 2 (N) POOL/SPA (512 SF) W POOL COVER 14' X 27.5' & 7' X 7' PER STANDARD PLAN #268 AND ENGIMEER DETAIL
Permit Issued
Issued on 1/27/2023
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2023 APPLICANT
Assigned to Plan Check Engineer 1/13/2023 JOSEPH RAFOLS
Corrections Issued 1/13/2023 JOSEPH RAFOLS
Plan Check Approved 1/27/2023 KHUONG TRUONG
Issued 1/27/2023 APPLICANT
CofO in Progress 8/12/2024 ENRIQUE MIRELES
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/27/2023 JOSEPH RAFOLS

Contact Information

Contractor Wavecrest Pools Inc; Lic. No.: 881346-C53 5320 DERRY AVENUE SUITE B      AGOURA HILLS, CA 91301
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 5/19/2023 Partial Approval JOSEPH MCGARRY
Pool Piping 5/19/2023 Partial Approval JOSEPH MCGARRY
Pre-Gunite 5/19/2023 Conditional Approval JOSEPH MCGARRY
Gas Piping or Gas Test 7/20/2023 Not Ready for Inspection JOSEPH MCGARRY
Pool Piping 7/20/2023 Approved JOSEPH MCGARRY
Rough-Electrical 7/20/2023 Approved JOSEPH MCGARRY
Deck 4/5/2024 Approved JEFFREY MEAD
Grounding or Bonding 4/5/2024 Partial Approval JEFFREY MEAD
Enclosure/Fence 4/17/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Not Ready ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/4/2024 Approved ENRIQUE MIRELES
Final 6/4/2024 Corrections Issued ENRIQUE MIRELES
Pre-Gunite 6/4/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Approved ENRIQUE MIRELES
Final 8/6/2024 Corrections Issued HAMIK HARTOUNIAN
Final 8/9/2024 OK to Issue CofO ENRIQUE MIRELES