2522 N MT BEACON TER 90068
Certificate Information: 2522 N MT BEACON TER 90068
- Application / Permit
- 23047-10000-00052
- Plan Check / Job No.
- B23LA00400
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL WITH BUILT IN AUTOMATIC POOL COVER AND POOL EQUIPEMENT
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | CARLOS MONTES |
| Corrections Issued | 2/6/2023 | CARLOS MONTES |
| Quality Review Completed | 2/9/2023 | KEN GILL |
| Building Plans Picked Up | 2/15/2023 | APPLICANT |
| Applicant returned to address corrections | 6/22/2023 | CARLOS MONTES |
| Plan Check Approved | 8/11/2023 | CARLOS MONTES |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 6/6/2025 | CRAIG VAUGHAN |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
| CofO Issued | 6/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 5/19/2023 | DANALYNN DOMINGUEZ |
| Grading Pre-Inspection | Cleared | 8/11/2023 | CARLOS MONTES |
Contact Information
| Contractor | Design Management And Construction Services; Lic. No.: 856999-B | 26007 HUNTINGTON LANE STE 7 VALENCIA, CA 91355 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 5/20/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Pre-Inspection | 5/20/2024 | Partial Inspection | BRENDAN MORELLI |
| Piling/Pier/Caisson | 7/22/2024 | Corrections Issued | ROY SPAULDING |
| Deputy Other (see comments) | 7/23/2024 | Conditional Approval | ROY SPAULDING |
| Piling/Pier/Caisson | 7/25/2024 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 8/5/2024 | Approved | ROY SPAULDING |
| Deputy Other (see comments) | 8/6/2024 | Conditional Approval | ROY SPAULDING |
| PLUMBING-Final | 8/15/2024 | Not Ready for Inspection | ROY SPAULDING |
| Pool Piping | 8/15/2024 | Approved | ROY SPAULDING |
| Pre-Gunite | 8/15/2024 | Approved | ROY SPAULDING |
| Rough-Plumbing | 8/15/2024 | Approved | ROY SPAULDING |
| Special/Order Compliance | 8/16/2024 | Not Ready for Inspection | ROY SPAULDING |
| Deputy Shotcrete | 8/19/2024 | Conditional Approval | ROY SPAULDING |
| Gas Piping or Gas Test | 11/1/2024 | Approved | CRAIG VAUGHAN |
| Grounding or Bonding | 11/4/2024 | Approved | CRAIG VAUGHAN |
| Deputy Shotcrete | 11/14/2024 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Steel/Welding | 11/19/2024 | Conditional Approval | CRAIG VAUGHAN |
| Enclosure/Fence | 2/18/2025 | Corrections Issued | CRAIG VAUGHAN |
| Enclosure/Fence | 2/19/2025 | Approved | CRAIG VAUGHAN |
| Pool Equipment Noise Test | 3/4/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Equipment Noise Level | 3/11/2025 | Approved | ANDEY CHAPARRO |
| Final | 3/12/2025 | Corrections Issued | CRAIG VAUGHAN |
| Final | 3/14/2025 | Conditional Approval | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 5/27/2025 | OK to Issue CofO | CRAIG VAUGHAN |