4437 N CALHOUN AVE 91423
Certificate Information: 4437 N CALHOUN AVE 91423
- Application / Permit
- 23047-10000-00030
- Plan Check / Job No.
- B22LA23366
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) SWIMMING POOL AND SPA (PER STANDARD PLAN #268) 3 OF 3
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | ADRIANA LOPEZ |
| Corrections Issued | 1/5/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 1/25/2023 | CHAD DOI |
| Applicant returned to address corrections | 5/31/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 6/15/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 6/27/2023 | ADRIANA LOPEZ |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 7/2/2025 | JAVIER RAMOS JR |
| CofO in Progress | 7/10/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 3/30/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/30/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Corrections Issued | JOHN COLEMAN |
| Gas Piping or Gas Test | 6/26/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Grounding or Bonding | 6/26/2024 | Approved | JOHN COLEMAN |
| Rough-Electrical | 6/26/2024 | Partial Approval | JOHN COLEMAN |
| Rough-Plumbing | 6/26/2024 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 7/1/2024 | Corrections Issued | JACK KARGODORIAN |
| Grounding or Bonding | 7/1/2024 | Partial Approval | JACK KARGODORIAN |
| Rough-Electrical | 7/1/2024 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Approved | MISAEL ESPARZA |
| Rough-Electrical | 7/9/2024 | Approved | MISAEL ESPARZA |
| Rough-Plumbing | 7/9/2024 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 5/6/2025 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 5/14/2025 | Corrections Issued | JOSE AVILA |
| Enclosure/Fence | 5/15/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Grounding or Bonding | 5/15/2025 | Corrections Issued | MISAEL ESPARZA |
| Deck | 5/16/2025 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 5/23/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/1/2025 | Approved | JACK KARGODORIAN |
| Final | 7/1/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 7/1/2025 | Approved | JACK KARGODORIAN |
| Pool Equipment Noise Test | 7/1/2025 | Approved | FELIPE PENICHE |
| Pre-Gunite | 7/1/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | JACK KARGODORIAN |
| Final | 7/2/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Final | 7/9/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |