2029 S CENTURY PARK EAST 2800 90067

Certificate Information: 2029 S CENTURY PARK EAST 2800 90067

Application / Permit
23041-10000-44033
Plan Check / Job No.
E23LA06324
Group
Electrical
Type
Electrical
Sub-Type
Commercial
Primary Use
()
Work Description
T.I. PC FOR T-24 ENERGY COMPLIANCE IN AN (E) HIGHT RISE BUILDING ON THE 28TH FL.
Permit Issued
Issued on 7/20/2023
Issuing Office
Current Status
Permit Finaled on 1/23/2024

Permit Application Status History

Submitted 7/19/2023 APPLICANT
Assigned to Plan Check Engineer 7/19/2023 AMMAR UL HASSAN
Plan Check Approved 7/19/2023 AMMAR UL HASSAN
Issued 7/20/2023 APPLICANT
Permit Finaled 1/22/2024 JOHN SPRINGER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor R & R Electric; Lic. No.: 472711-C10 2803 CARLSBAD      REDONDO BEACH, CA 90278
Engineer Sarmiento,, Chris Leal; Lic. No.: E11808 35 N HOBSON ST      GILBERT, AZ 85233

Inspector Information

GEORGE LELEA, (310) 914-3942 Office Hours: 7:00-8:00 AM MON-FRI
GONZALO GARCIA, (310) 914-3942 Office Hours: 7:00-8:00 AM MON-FRI
VICTOR PUKHALSKY, (310) 914-3942 Office Hours: 7:00-8:00 AM MON-FRI
DAVID KOSKI, (310) 914-3942 Office Hours: 7:00-8:00 AM MON-FRI
JAKE MARTINEK, (310) 914-3942 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough 7/24/2023 Partial Approval ANTHONY MCDOWALL
Rough 8/1/2023 Partial Approval JOHN SPRINGER
Rough 8/22/2023 Partial Approval JOHN SPRINGER
Rough 8/24/2023 Corrections Issued JOHN SPRINGER
Rough 8/29/2023 Partial Approval ANTHONY MCDOWALL
T-Bar Ceiling 8/29/2023 Partial Approval ANTHONY MCDOWALL
Rough 8/31/2023 Partial Approval JOHN SPRINGER
Rough 9/5/2023 Partial Approval JOHN SPRINGER
Rough 9/8/2023 Partial Approval JOHN SPRINGER
T-Bar Ceiling 9/8/2023 Partial Approval JOHN SPRINGER
T-Bar Ceiling 9/18/2023 Partial Approval JOHN SPRINGER
T-Bar Ceiling 9/25/2023 Partial Approval ANTHONY MCDOWALL
Final 10/11/2023 Conditional Approval JOHN SPRINGER
Special/Order Compliance 10/20/2023 Partial Inspection MICHAEL TILK
Rough 10/25/2023 Corrections Issued JOHN SPRINGER
Rough 10/30/2023 Corrections Issued JOHN SPRINGER
Rough 12/28/2023 Approved MICHAEL TILK
T-Bar Ceiling 12/28/2023 Approved MICHAEL TILK
Final 1/22/2024 Permit Finaled JOHN SPRINGER