2029 S CENTURY PARK EAST 29TH FLOOR 90067
Certificate Information: 2029 S CENTURY PARK EAST 29TH FLOOR 90067
- Application / Permit
- 23041-10000-43998
- Plan Check / Job No.
- E23LA06323
- Group
- Electrical
- Type
- Electrical
- Sub-Type
- Commercial
- Primary Use
- ()
- Work Description
- PLAN CHECK FOR ENERGY COMPLIANCE ONLY. SCOPE OF WORK IS A T.I OF AN EXISTING COMMERCIAL SPACE'S 29TH FLOOR AND COVERS LIGHTING AND CIRCUITS. TOTAL INDOOR LIGHTING AREA IS APPROXIMATELY: 15,862 SQFT AND TOTAL NEW LOAD IS LESS THAN 400A.
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/23/2024
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2023 | STEVEN WRIGHT |
| Plan Check Approved | 7/19/2023 | STEVEN WRIGHT |
| Issued | 7/20/2023 | APPLICANT |
| Permit Finaled | 1/22/2024 | JOHN SPRINGER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | R & R Electric; Lic. No.: 472711-C10 | 2803 CARLSBAD REDONDO BEACH, CA 90278 |
| Engineer | Sarmiento,, Chris Leal; Lic. No.: E11808 | 35 N HOBSON ST GILBERT, AZ 85233 |
Inspector Information
| GEORGE LELEA, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| GONZALO GARCIA, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| VICTOR PUKHALSKY, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID KOSKI, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAKE MARTINEK, (310) 914-3942 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough | 7/24/2023 | Partial Approval | ANTHONY MCDOWALL |
| Rough | 8/10/2023 | Partial Approval | JOHN SPRINGER |
| Rough | 8/15/2023 | Partial Approval | JOHN SPRINGER |
| Rough | 8/29/2023 | Partial Approval | ANTHONY MCDOWALL |
| T-Bar Ceiling | 8/29/2023 | Partial Approval | ANTHONY MCDOWALL |
| Rough | 9/5/2023 | Partial Approval | JOHN SPRINGER |
| T-Bar Ceiling | 9/5/2023 | Approved | JOHN SPRINGER |
| T-Bar Ceiling | 9/8/2023 | Partial Approval | JOHN SPRINGER |
| Rough | 10/6/2023 | Partial Approval | JOHN SPRINGER |
| Final | 10/11/2023 | Conditional Approval | JOHN SPRINGER |
| Rough | 10/19/2023 | Partial Approval | ANTHONY MCDOWALL |
| Special/Order Compliance | 10/20/2023 | Partial Inspection | MICHAEL TILK |
| Rough | 10/31/2023 | Partial Approval | JOHN SPRINGER |
| Rough | 12/15/2023 | Partial Approval | JOHN SPRINGER |
| T-Bar Ceiling | 12/15/2023 | Partial Approval | JOHN SPRINGER |
| Rough | 12/22/2023 | Partial Approval | JOHN SPRINGER |
| T-Bar Ceiling | 12/22/2023 | Partial Approval | JOHN SPRINGER |
| Final | 1/22/2024 | Permit Finaled | JOHN SPRINGER |