1430 S HOLMBY AVE 90024
Certificate Information: 1430 S HOLMBY AVE 90024
- Application / Permit
- 23030-30000-05557
- Plan Check / Job No.
- B23WL02241
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for new retaining wall. "COMPLY WITH DEPARTMENT ORDER effective date 09/18/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 3/9/2026
Permit Application Status History
| Submitted | 9/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 9/18/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 9/26/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/29/2023 | APPLICANT |
| Applicant returned to address corrections | 5/14/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 8/30/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 10/4/2024 | HOOMAN HAJIZADEH |
| Issued | 10/4/2024 | APPLICANT |
| Permit Finaled | 3/9/2026 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/14/2024 | HOOMAN HAJIZADEH |
| Construction within easement | Cleared | 6/26/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Areio Inc; Lic. No.: 997015-B | 73 NIGHTHAWK IRVINE, CA 92604 |
| Engineer | Al-Omar,, Abdel-Jabbar Jamal; Lic. No.: C41683 | 2973 HARBOR BLVD 458 COSTA MESA, CA 92626 |
| Engineer | Eftekhari,, Hossein; Lic. No.: C50121 | 5945 SETTLER COURT ANAHEIM, CA 92807 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/23/2024 | Approved | RUSSELL BONVOULOIR |
| Initial Grading | 5/27/2025 | No Access for Inspection | ROBERT PINA |
| Initial Grading | 6/2/2025 | Not Ready for Inspection | LANNY MERRICK |
| Initial Grading | 6/3/2025 | Corrections Issued | LANNY MERRICK |
| Initial Grading | 12/2/2025 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 12/2/2025 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 12/15/2025 | Approved | JOHNNY MIRANDA |
| Final | 12/15/2025 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 12/15/2025 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 1/6/2026 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 3/6/2026 | Approved | JESUS RODRIGUEZ |
| Final | 3/9/2026 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |