1600 N RISING GLEN ROAD 90069

Certificate Information: 1600 N RISING GLEN ROAD 90069

Application / Permit
23030-30000-04587
Plan Check / Job No.
B23WL01891
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Site grading for SFD addition, ADU and backfill (e) pool with structural fill
Permit Issued
Issued on 12/28/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 9/25/2025

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 REZA HAGHIGHAT
Corrections Issued 7/30/2023 REZA HAGHIGHAT
Quality Review Completed 8/9/2023 KAVIAN REFAHI
Building Plans Picked Up 8/10/2023 APPLICANT
Plan Check Approved 12/19/2023 REZA HAGHIGHAT
Issued 12/28/2023 APPLICANT
Permit Finaled 9/25/2025 ROBERT PINA

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 12/19/2023 CALOSHA APPROVED
Grading Pre-Inspection Cleared 12/19/2023 REZA HAGHIGHAT

Contact Information

Contractor Dosh Construction Inc; Lic. No.: 1064567-B 14721 OXNARD ST      VAN NUYS, CA 91411
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 1/25/2024 Corrections Issued ALEXANDER HELFER
Bottom/Toe 5/31/2024 Partial Approval ALEXANDER HELFER
Bottom/Toe 7/23/2025 Corrections Issued ROBERT PINA
Final 7/23/2025 Not Ready for Inspection ROBERT PINA
Rough 7/23/2025 Not Ready for Inspection ROBERT PINA
Bottom/Toe 7/25/2025 Corrections Issued ROBERT PINA
Final 7/25/2025 Not Ready for Inspection ROBERT PINA
Rough 7/25/2025 Not Ready for Inspection ROBERT PINA
Approved Compaction Report 8/6/2025 Approved ROBERT PINA
Bottom/Toe 9/12/2025 Not Ready for Inspection ROBERT PINA
Final 9/12/2025 Not Ready for Inspection ROBERT PINA
Rough 9/12/2025 Not Ready for Inspection ROBERT PINA
Bottom/Toe 9/25/2025 Approved ROBERT PINA
Final 9/25/2025 Permit Finaled ROBERT PINA
Rough 9/25/2025 Approved ROBERT PINA