1630 S CREST DR 90035

Certificate Information: 1630 S CREST DR 90035

Application / Permit
23030-30000-03444
Plan Check / Job No.
B23WL01448
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
Grading for (N) retaining wall at backyard *** 2 of 2 ***
Permit Issued
Issued on 8/21/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 8/13/2024

Permit Application Status History

Submitted 6/1/2023 APPLICANT
Assigned to Plan Check Engineer 6/7/2023 YASHAR EMAMI
Corrections Issued 6/16/2023 YASHAR EMAMI
Quality Review Completed 6/27/2023 KAVIAN REFAHI
Building Plans Picked Up 6/29/2023 APPLICANT
Applicant returned to address corrections 7/19/2023 YASHAR EMAMI
Applicant returned to address corrections 7/28/2023 YASHAR EMAMI
Plan Check Approved 8/21/2023 YASHAR EMAMI
Issued 8/21/2023 APPLICANT
Permit Finaled 8/12/2024 JONATHAN HOM

Permit Application Clearance Information

GPI Written Notices Cleared 7/19/2023 YASHAR EMAMI
Grading Pre-Inspection Cleared 7/19/2023 YASHAR EMAMI
ZA Case Cleared 7/24/2023 DALIA MOKAYED
Roof/Waste drainage to street Cleared 7/29/2023 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 8/2/2023 TERRY PHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 9/5/2023 Corrections Issued JONATHAN HOM
Excavation 9/5/2023 Partial Inspection JONATHAN HOM
Initial Grading 9/5/2023 Partial Inspection JONATHAN HOM
Bottom/Toe 9/7/2023 Partial Inspection JONATHAN HOM
Excavation 9/7/2023 Partial Inspection JONATHAN HOM
Bottom/Toe 9/11/2023 Partial Inspection JONATHAN HOM
Excavation 9/11/2023 Corrections Issued JONATHAN HOM
Excavation 9/12/2023 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 9/13/2023 Partial Approval JONATHAN HOM
Excavation 9/13/2023 Partial Inspection JONATHAN HOM
Drainage Devices/Catch Basin 11/14/2023 Conditional Approval RUSSELL BONVOULOIR
Approved Compaction Report 6/13/2024 Approved JONATHAN HOM
Bottom/Toe 7/11/2024 Not Ready for Inspection JONATHAN HOM
Final 7/11/2024 Not Ready for Inspection JONATHAN HOM
Rough 7/11/2024 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 8/12/2024 Approved JONATHAN HOM
Final 8/12/2024 Permit Finaled JONATHAN HOM
Rough 8/12/2024 Approved JONATHAN HOM
Sub-Drain 8/12/2024 Approved JONATHAN HOM