2712 S MONTE MAR TER 90064
Certificate Information: 2712 S MONTE MAR TER 90064
- Application / Permit
- 23030-20000-07181
- Plan Check / Job No.
- B23VN15917
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING PERMIT FOR SITE PREP, R&R FOR PROPOSED 2-STORY SFD AND BACKFILL RET. WALL
- Permit Issued
- Issued on 2/27/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/27/2024
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | SEAN SHAHMIRI |
| Corrections Issued | 11/30/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 12/7/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/7/2023 | APPLICANT |
| Applicant returned to address corrections | 1/22/2024 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/2/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 2/26/2024 | SEAN SHAHMIRI |
| Issued | 2/27/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | A&N Developments; Lic. No.: 1101931-B | 252 TRIANGLE ST THOUSAND OAKS, CA 91360 |
| Engineer | Andrada,, Aprile; Lic. No.: C81097 | 27240 TURNBERRY LANE VALENCIA, CA 91355 |
| Engineer | Tani,, Jason; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/4/2024 | Corrections Issued | JOHNNY MIRANDA |
| Initial Grading | 3/6/2024 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 3/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 3/13/2024 | Conditional Approval | MATTHEW JENKINS |
| Excavation | 3/13/2024 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 3/14/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/15/2024 | Conditional Approval | MATTHEW JENKINS |
| Approved Compaction Report | 4/23/2024 | Approved | MATTHEW JENKINS |
| Sub-Drain | 6/4/2024 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 12/29/2025 | Approved | LANNY MERRICK |