820 S GLENMONT AVE 90024

Certificate Information: 820 S GLENMONT AVE 90024

Application / Permit
23030-20000-06177
Plan Check / Job No.
B23VN13592
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW RETAINING WALL
Permit Issued
Issued on 11/3/2023
Issuing Office
Valley
Current Status
Permit Finaled on 3/19/2025

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 KAMYAR EMAMI
Corrections Issued 10/12/2023 KAMYAR EMAMI
Building Plans Picked Up 10/17/2023 APPLICANT
Issued 11/3/2023 APPLICANT
Permit Finaled 3/18/2025 JOHNNY MIRANDA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 1/10/2024 Partial Inspection MATTHEW JENKINS
Fill/Backfill 1/10/2024 Partial Inspection MATTHEW JENKINS
Initial Grading 1/10/2024 Partial Inspection MATTHEW JENKINS
Excavation 1/30/2024 Partial Inspection AL GAMBLE
Initial Grading 1/30/2024 Not Ready for Inspection AL GAMBLE
Rough 1/30/2024 Approved AL GAMBLE
Excavation 3/29/2024 Partial Approval MATTHEW JENKINS
Initial Grading 3/29/2024 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 4/9/2024 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 4/9/2024 Partial Inspection MATTHEW JENKINS
Fill/Backfill 4/9/2024 Partial Inspection MATTHEW JENKINS
Sub-Drain 4/9/2024 Partial Approval MATTHEW JENKINS
Bottom/Toe 12/5/2024 Partial Inspection MATTHEW JENKINS
Final 12/5/2024 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 12/17/2024 Approved MATTHEW JENKINS
Bottom/Toe 12/19/2024 Approved MATTHEW JENKINS
Final 12/19/2024 Not Ready for Inspection MATTHEW JENKINS
Final 1/6/2025 Not Ready for Inspection AL GAMBLE
Approved Compaction Report 2/7/2025 Approved JOHNNY MIRANDA
Final 2/10/2025 Corrections Issued VASIL MIHALEV
Final 2/26/2025 Not Ready for Inspection AL GAMBLE
Final 3/3/2025 Partial Inspection JOHNNY MIRANDA
Final 3/18/2025 Permit Finaled JOHNNY MIRANDA