9411 W KIRKSIDE ROAD 90035
Certificate Information: 9411 W KIRKSIDE ROAD 90035
- Application / Permit
- 23030-20000-04870
- Plan Check / Job No.
- B23VN10521
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING EXCAVATION FOR BASMENT AND R & R
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 7/1/2026
Permit Application Status History
| Submitted | 8/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | RAPHAEL ROSAS |
| Corrections Issued | 8/30/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 9/8/2023 | STEVEN KIM |
| Applicant returned to address corrections | 1/22/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/8/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/14/2024 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/21/2024 | APPLICANT |
| Applicant returned to address corrections | 3/28/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/3/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 4/15/2024 | RAPHAEL ROSAS |
| Issued | 4/15/2024 | APPLICANT |
| Permit Finaled | 7/1/2026 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 4/3/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/3/2024 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 4/3/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 4/30/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Bottom/Toe | 5/10/2024 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 5/10/2024 | Partial Inspection | MATTHEW JENKINS |
| Rough | 5/10/2024 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 5/22/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Sub-Drain | 5/24/2024 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 5/29/2024 | Partial Approval | MATTHEW JENKINS |
| Fill/Backfill | 11/5/2024 | Partial Approval | AL GAMBLE |
| Sub-Drain | 11/5/2024 | Partial Approval | AL GAMBLE |
| Approved Compaction Report | 2/4/2025 | Corrections Issued | JOHNNY MIRANDA |
| Approved Compaction Report | 3/11/2025 | Corrections Issued | MATTHEW JENKINS |
| Special/Order Compliance | 7/28/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 5/29/2026 | Approved | JESUS RODRIGUEZ |
| Bottom/Toe | 6/15/2026 | Approved | JOHNNY MIRANDA |
| Final | 6/15/2026 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 6/15/2026 | Approved | JOHNNY MIRANDA |
| Final | 6/25/2026 | Not Ready for Inspection | LANNY MERRICK |
| Final | 6/26/2026 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 7/1/2026 | Permit Finaled | JOHNNY MIRANDA |