2718-2720 S MONTE MAR TER 90064
Certificate Information: 2718-2720 S MONTE MAR TER 90064
- Application / Permit
- 23030-20000-04419
- Plan Check / Job No.
- B23VN09503
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR BASEMENT ADDITIONS, RETAINING WALL, REC ROOM
- Permit Issued
- Issued on 10/5/2023
- Issuing Office
- Valley
- Current Status
- Issued on 10/5/2023
Permit Application Status History
| Submitted | 7/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/25/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 7/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/27/2023 | APPLICANT |
| Plan Check Approved | 10/5/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/5/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | ANTHONY MAINEZ |
| Excavation more than 5-ft deep | Cleared | 9/29/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/29/2023 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 9/29/2023 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Architect | Larkin,, Dean A; Lic. No.: C28277 | 8912 HOLLYWOOD HILLS RD LOS ANGELES, CA 90046 |
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5168 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/30/2023 | Corrections Issued | MATTHEW JENKINS |
| Initial Grading | 11/7/2023 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 12/8/2023 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 3/28/2024 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 11/14/2024 | Approved | VASIL MIHALEV |
| Sub-Drain | 3/27/2025 | Partial Approval | AL GAMBLE |
| Final | 7/27/2026 | Corrections Issued | JOHNNY MIRANDA |
| Bottom/Toe | 7/28/2026 | Approved | JOHNNY MIRANDA |
| Final | 7/28/2026 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough | 7/28/2026 | Approved | JOHNNY MIRANDA |