965 N STALEY LANE 90042
Certificate Information: 965 N STALEY LANE 90042
- Application / Permit
- 23030-20000-02109
- Plan Check / Job No.
- B18VN07039
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING - SITE PREP FOR NEW SFD
- Permit Issued
- Issued on 9/22/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/1/2025
Permit Application Status History
| Submitted | 4/26/2018 | APPLICANT |
| Green Plans Picked Up | 5/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2018 | RAPHAEL ROSAS |
| Corrections Issued | 5/19/2018 | RAPHAEL ROSAS |
| Quality Review Completed | 5/25/2018 | STEVEN KIM |
| Building Plans Picked Up | 5/30/2018 | APPLICANT |
| Applicant returned to address corrections | 9/10/2018 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/10/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/11/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/31/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/10/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 5/12/2023 | RAPHAEL ROSAS |
| Issued | 9/22/2023 | APPLICANT |
| Permit Finaled | 8/1/2025 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 4/14/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 4/14/2023 | NATHAN ROMINE |
| Grading Pre-Inspection | Cleared | 5/10/2023 | RAPHAEL ROSAS |
Contact Information
| Contractor | S K L Construction; Lic. No.: 958490-B | PO BOX 9559 RANCHO CUCAMONGA, CA 91701 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 11/7/2023 | Approved | ROBERT HUGHES |
| Initial Grading | 12/15/2023 | Approved | RUSSELL BONVOULOIR |
| Special/Order Compliance | 12/27/2024 | Partial Inspection | LANNY MERRICK |
| Sub-Drain | 4/24/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 6/27/2025 | Conditional Approval | RAMAZANALI ALMASI |
| Approved Compaction Report | 7/28/2025 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 8/1/2025 | Approved | RAMAZANALI ALMASI |
| Final | 8/1/2025 | Permit Finaled | RAMAZANALI ALMASI |
| Rough | 8/1/2025 | Approved | RAMAZANALI ALMASI |