2383 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 2383 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 23030-20000-02090
- Plan Check / Job No.
- B23VN03408
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE PREP. GRADING FOR NEW SINGLE FAMILY DWELLING W/BASEMENT, DET. ACCESSORY LIVING QUARTERS, RETAINING WALL, SPORTS COURT, POOL
- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Valley
- Current Status
- Issued on 12/28/2023
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | PETER MOSESIAN |
| Corrections Issued | 3/31/2023 | PETER MOSESIAN |
| Quality Review Completed | 3/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 4/20/2023 | APPLICANT |
| Plan Check Approved | 12/19/2023 | PETER MOSESIAN |
| Issued | 12/28/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | DARIN LAM |
| Watercourse | Cleared | 6/28/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Radziner,, Ronald Mark; Lic. No.: C22228 | MARMOL RADZINER & ASSOCIATES 12210 NEBRASKA AVE LOS ANGELES, CA 90025 |
| Contractor | J R C Group Inc; Lic. No.: 980658-B | 8981 SUNSET BLVD STE 505 LOS ANGELES, CA 90069 |
| Engineer | Arca,, Perfecto; Lic. No.: C28918 | 23222 ROSANNA COURT TORRANCE, CA 90502 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 12/29/2023 | Partial Approval | JOHNNY MIRANDA |
| Initial Grading | 12/29/2023 | Corrections Issued | JOHNNY MIRANDA |
| Bottom/Toe | 1/11/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 1/26/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 2/13/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 2/29/2024 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 2/29/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 3/11/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation | 3/12/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 3/13/2024 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 3/29/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 4/18/2024 | Partial Approval | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 4/18/2024 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sub-Drain | 4/18/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 4/23/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 5/3/2024 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 5/22/2024 | Partial Approval | AL GAMBLE |
| Approved Compaction Report | 7/22/2024 | Approved | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 7/29/2024 | Approved | VASIL MIHALEV |
| Sub-Drain | 7/29/2024 | Approved | VASIL MIHALEV |
| Bottom/Toe | 10/1/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 10/3/2024 | Partial Approval | JOHNNY MIRANDA |
| Sub-Drain | 10/3/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 10/25/2024 | Partial Approval | AL GAMBLE |