1461 N AMALFI DR 90272

Certificate Information: 1461 N AMALFI DR 90272

Application / Permit
23030-20000-02021
Plan Check / Job No.
B23VN03929
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING PERMIT FOR SITE PREP, EXCAVATION FOR PROPOSED SFD & SWIMMING POOL AND BACKFILL NEW RET WALL [BF 220008 APPROVED FOR AN EXPORT OF 3,045 CUBIC YARDS]
Permit Issued
Issued on 10/16/2023
Issuing Office
West Los Angeles
Current Status
Issued on 10/16/2023

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 SEAN SHAHMIRI
Corrections Issued 4/27/2023 SEAN SHAHMIRI
Quality Review Completed 4/28/2023 OMID HEDAYAT
Building Plans Picked Up 4/28/2023 APPLICANT
Applicant returned to address corrections 8/7/2023 SEAN SHAHMIRI
Applicant returned to address corrections 8/31/2023 SEAN SHAHMIRI
Plan Check Approved 10/10/2023 SEAN SHAHMIRI
Issued 10/16/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/7/2023 DINAH GARIN
Work Adjacent to Public Way Cleared 6/15/2023 LIAM ODONOVAN
Excavation more than 5-ft deep Cleared 8/31/2023 CALOSHA APPROVED
ZA Case Cleared 9/1/2023 MAXFIELD VERMY
Haul Route Cleared 10/3/2023 ALAN MORELOS

Contact Information

Architect Ziebell,, Donald Swen; Lic. No.: C24177 OZ ARCHITECTS INC.   7401 E. REDFIELD RD.    SCOTTSDALE, AZ 85260
Contractor Jones Builders Group Inc; Lic. No.: 904861-B 23823 MALIBU RD 50-375      MALIBU, CA 90265
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 11/1/2023 Corrections Issued JOHNNY MIRANDA
Initial Grading 12/8/2023 Approved RUSSELL BONVOULOIR
Sub-Drain 9/20/2024 Partial Approval JOHNNY MIRANDA
Fill/Backfill 9/26/2024 Partial Approval JOHNNY MIRANDA
Sub-Drain 9/26/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 10/4/2024 Partial Approval JOHNNY MIRANDA
Excavation 10/4/2024 Partial Approval JOHNNY MIRANDA
Fill/Backfill 10/4/2024 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 11/5/2024 Approved MATTHEW JENKINS