2003 N LA BREA TER 90046

Certificate Information: 2003 N LA BREA TER 90046

Application / Permit
23030-20000-01846
Plan Check / Job No.
B23VN03643
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING PERMIT FOR GRADING WORK TO REPLACE (E) DRIVEWAY AND BACKFILL NEW RETAINING WALL ON PILES
Permit Issued
Issued on 8/7/2023
Issuing Office
Valley
Current Status
Permit Finaled on 2/29/2024

Permit Application Status History

Submitted 3/22/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 SEAN SHAHMIRI
Corrections Issued 4/6/2023 SEAN SHAHMIRI
Quality Review Completed 4/6/2023 OMID HEDAYAT
Building Plans Picked Up 4/10/2023 APPLICANT
Quality Review Completed 5/8/2023 OMID HEDAYAT
Applicant returned to address corrections 5/11/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/12/2023 SEAN SHAHMIRI
Plan Check Approved 7/20/2023 SEAN SHAHMIRI
Issued 8/7/2023 APPLICANT
Permit Finaled 2/28/2024 ALEXANDER HELFER

Permit Application Clearance Information

HPOZ Cleared 4/12/2023 MAX LODER
Grading Pre-Inspection Cleared 8/7/2023 SEAN SHAHMIRI

Contact Information

Contractor Blaha Construction & Development; Lic. No.: 595743-B 28376 CONSTELLATION ROAD      VALENCIA, CA 91355
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/9/2023 Approved ALEXANDER HELFER
Excavation 9/14/2023 Approved ALEXANDER HELFER
Deputy Other (see comments) 9/15/2023 Approved ALEXANDER HELFER
Excavation 9/25/2023 Approved ALEXANDER HELFER
Deputy Other (see comments) 9/26/2023 Approved ALEXANDER HELFER
Initial Grading 10/11/2023 Approved ALEXANDER HELFER
Deputy Grading 10/12/2023 Approved ALEXANDER HELFER
Sub-Drain 10/24/2023 Approved ALEXANDER HELFER
Bottom/Toe 12/21/2023 Approved RUSSELL BONVOULOIR
Final 12/21/2023 Not Ready for Inspection RUSSELL BONVOULOIR
Rough 12/21/2023 Approved RUSSELL BONVOULOIR
Approved Compaction Report 2/9/2024 Approved ALEXANDER HELFER
Final 2/28/2024 Permit Finaled ALEXANDER HELFER