400 N CARMELINA AVE 90049

Certificate Information: 400 N CARMELINA AVE 90049

Application / Permit
23030-20000-01843
Plan Check / Job No.
B23VN03628
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
SITE GRADING FOR SFD, ADU, POOL, AND RETAINING WALLS (3 OF 6)
Permit Issued
Issued on 11/6/2023
Issuing Office
Valley
Current Status
Issued on 11/6/2023

Permit Application Status History

Submitted 3/22/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 MARVEL DELACRUZ
Corrections Issued 4/6/2023 MARVEL DELACRUZ
Quality Review Completed 4/6/2023 OMID HEDAYAT
Building Plans Picked Up 4/7/2023 APPLICANT
Applicant returned to address corrections 4/18/2023 MARVEL DELACRUZ
Applicant returned to address corrections 5/22/2023 MARVEL DELACRUZ
Applicant returned to address corrections 7/21/2023 MARVEL DELACRUZ
Applicant returned to address corrections 10/11/2023 MARVEL DELACRUZ
Applicant returned to address corrections 11/2/2023 MARVEL DELACRUZ
Plan Check Approved 11/6/2023 MARVEL DELACRUZ
Issued 11/6/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 4/11/2023 RUBEN VASQUEZ

Contact Information

Contractor Tatum Construction Inc; Lic. No.: 733806-B 1909 CENTINELA AVENUE      SANTA MONICA, CA 90404
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 11/8/2023 Corrections Issued CHARLES POWELL
Initial Grading 11/13/2023 Partial Approval CHARLES POWELL
Sub-Drain 2/26/2024 Partial Approval ROBERT PINA
Sub-Drain 5/6/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 5/9/2024 Partial Approval JOHNNY MIRANDA
Sub-Drain 5/20/2024 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 5/28/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 6/10/2024 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 8/12/2024 Partial Approval JOHNNY MIRANDA
Sub-Drain 9/13/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 9/27/2024 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 10/8/2024 Partial Approval JOHNNY MIRANDA
Bottom/Toe 10/15/2024 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 10/23/2024 Not Ready for Inspection JOHNNY MIRANDA
Approved Compaction Report 11/4/2024 Approved MATTHEW JENKINS
Approved Compaction Report 6/12/2026 Approved GERMAN RODRIGUEZ MENDOZA