4954 N BILOXI AVE 91601

Certificate Information: 4954 N BILOXI AVE 91601

Application / Permit
23030-20000-01386
Plan Check / Job No.
B23VN02770
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
ePlan GRADING PERMIT FOR 22010-20000-06476 AND 23010-20000-00515 CUT: 417. CUBIC YARDS FILL: 197 CUBIC YARDS REMOVAL AND RECOMPACTION: 364 CUBIC YARDS NET (EXPORT): 220 CUBIC YARD
Permit Issued
Issued on 9/26/2024
Issuing Office
Current Status
Issued on 9/26/2024

Permit Application Status History

Submitted 3/6/2023 APPLICANT
Assigned to Plan Check Engineer 3/8/2023 SUNMIN LEE
Corrections Issued 3/14/2023 SUNMIN LEE
Applicant returned to address corrections 6/6/2023 SUNMIN LEE
Applicant returned to address corrections 6/24/2024 SUNMIN LEE
Applicant returned to address corrections 8/6/2024 SUNMIN LEE
Plan Check Approved 8/9/2024 SUNMIN LEE
Issued 9/26/2024 APPLICANT

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 4/19/2024 CALOSHA APPROVED

Contact Information

Contractor Cali Builders & Construction Inc; Lic. No.: 1051566-B       ,
Engineer Krief,, Dan D; Lic. No.: C76041 6420 WILSHIRE BLVD STE 1000      LOS ANGELES, CA 90048
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Soliman,, Magdi G; Lic. No.: L8822 19246 BENSION DR      SANTA CLARITA, CA 91350

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 11/18/2024 Corrections Issued MANUEL TEJADA
Bottom/Toe 3/7/2025 Approved MANUEL TEJADA
Deputy Grading 3/10/2025 Approved MANUEL TEJADA
Fill/Backfill 3/10/2025 Partial Approval MANUEL TEJADA
Deputy Grading 3/11/2025 Approved MANUEL TEJADA
Deputy Grading 3/12/2025 No Access for Inspection MANUEL TEJADA
Deputy Grading 3/17/2025 No Access for Inspection MANUEL TEJADA
Approved Compaction Report 4/28/2025 Approved ALEXANDER HELFER
Sub-Drain 11/3/2025 Approved ALEXANDER HELFER
Approved Compaction Report 2/27/2026 Not Ready for Inspection MATTHEW JENKINS
Approved Compaction Report 3/4/2026 Approved MATTHEW JENKINS
Approved Compaction Report 3/9/2026 Partial Inspection MATTHEW JENKINS
Final 4/7/2026 Partial Inspection MATTHEW JENKINS
Rough 4/7/2026 Partial Inspection MATTHEW JENKINS