12121 W FOOTHILL BLVD 91342
Certificate Information: 12121 W FOOTHILL BLVD 91342
- Application / Permit
- 23030-20000-01334
- Plan Check / Job No.
- B23VN02649
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- EXCAVATION/BACKFILL/R&R FOR (N) STORAGE BLDG -- HILLSIDE GRADING AREA **ePLAN**
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/26/2026
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/22/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/31/2023 | STEVEN KIM |
| Applicant returned to address corrections | 5/1/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/1/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/13/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/14/2023 | NILOOFAR MEHRAIN |
| Issued | 11/20/2023 | APPLICANT |
| Permit Finaled | 3/26/2026 | ALEXANDER HELFER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/22/2023 | NILOOFAR MEHRAIN |
| Miscellaneous | Cleared | 8/9/2023 | DANIEL CORONADO |
| Excavation more than 5-ft deep | Cleared | 8/15/2023 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 10/5/2023 | LEE GUILBEAUX |
| Haul Route | Cleared | 10/20/2023 | ALAN MORELOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2023 | EDGAR ALCARAZ |
| "Q" conditions | Cleared | 11/6/2023 | NELSON RODRIGUEZ |
| "T" removal | Cleared | 11/6/2023 | NELSON RODRIGUEZ |
| CPC | Cleared | 11/6/2023 | NELSON RODRIGUEZ |
| Roof/Waste drainage to street | Cleared | 11/9/2023 | ALEXANDER SBARDELLATI |
Contact Information
| Contractor | Arco / Murray National Construction Company Inc; Lic. No.: 934740-B | 3110 WOODCREEK DRIVE DOWNERS GROVE, IL 60515 |
| Engineer | Johnson,, Steven; Lic. No.: C83319 | 760 MILL ST SILVERTON, OR 97831 |
| Engineer | Zadoorian,, Christopher John; Lic. No.: GE2493 | 1431 MONTGOMEERY ST TUSTIN, CA 92782 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/4/2023 | Approved | MANUEL TEJADA |
| Deputy Grading | 1/8/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 1/9/2024 | Approved | MANUEL TEJADA |
| Bottom/Toe | 1/29/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 1/29/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 1/30/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 2/1/2024 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 2/2/2024 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 2/28/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 2/28/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 2/29/2024 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/1/2024 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 3/12/2024 | Approved | MANUEL TEJADA |
| Deputy Grading | 3/13/2024 | Approved | MANUEL TEJADA |
| Deputy Grading | 3/14/2024 | Approved | MANUEL TEJADA |
| Excavation | 3/14/2024 | Partial Approval | MANUEL TEJADA |
| Deputy Grading | 3/15/2024 | Partial Approval | CHARLES POWELL |
| Excavation | 3/18/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/19/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/20/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/21/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/22/2024 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 4/11/2024 | Corrections Issued | MANUEL TEJADA |
| Deputy Grading | 4/11/2024 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 4/16/2024 | Approved | ROBERT PINA |
| Deputy Grading | 5/21/2024 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 5/22/2024 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 5/23/2024 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 5/24/2024 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 5/31/2024 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 5/27/2025 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 6/2/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 6/16/2025 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 9/24/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 10/29/2025 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| SWPPP-Const. Storm Water | 11/4/2025 | Completed | ALEXANDER HELFER |
| Final | 3/12/2026 | Corrections Issued | CHARLES POWELL |
| Rough | 3/12/2026 | Approved | CHARLES POWELL |
| Approved Compaction Report | 3/23/2026 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 3/26/2026 | Approved | ALEXANDER HELFER |
| Final | 3/26/2026 | Permit Finaled | ALEXANDER HELFER |