200 N GUNSTON DR 90049

Certificate Information: 200 N GUNSTON DR 90049

Application / Permit
23030-20000-00417
Plan Check / Job No.
B22VN13709
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING WORK FOR BASEMENT, RETAINING WALL, DECK EXCAVATION, SITE PREP, AND R&R
Permit Issued
Issued on 6/23/2023
Issuing Office
Valley
Current Status
Permit Finaled on 2/22/2025

Permit Application Status History

Submitted 9/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 MARVEL DELACRUZ
Corrections Issued 9/25/2022 MARVEL DELACRUZ
Quality Review Completed 9/28/2022 OMID HEDAYAT
Applicant returned to address corrections 1/24/2023 MARVEL DELACRUZ
Building Plans Picked Up 4/19/2023 APPLICANT
Applicant returned to address corrections 4/24/2023 MARVEL DELACRUZ
Applicant returned to address corrections 5/26/2023 MARVEL DELACRUZ
Plan Check Approved 6/23/2023 MARVEL DELACRUZ
Issued 6/23/2023 APPLICANT
Permit Finaled 2/21/2025 MATTHEW JENKINS

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Stockton,, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Owner-Builder       ,
Engineer Berger,, Phillip Martin; Lic. No.: C13128 601 ARCADIA PL APT 203      NATIONAL CITY, CA 91950
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Approved Compaction Report 5/9/2024 Approved VASIL MIHALEV
Bottom/Toe 12/26/2024 Partial Inspection MATTHEW JENKINS
Final 12/26/2024 Partial Inspection MATTHEW JENKINS
Rough 12/26/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 1/30/2025 Partial Inspection MATTHEW JENKINS
Final 1/30/2025 Partial Inspection MATTHEW JENKINS
Rough 1/30/2025 Partial Inspection MATTHEW JENKINS
Bottom/Toe 2/11/2025 Approved MATTHEW JENKINS
Final 2/11/2025 Corrections Issued MATTHEW JENKINS
Rough 2/11/2025 Approved MATTHEW JENKINS
Final 2/21/2025 Permit Finaled MATTHEW JENKINS