4223 S DON CARLOS DR 90008

Certificate Information: 4223 S DON CARLOS DR 90008

Application / Permit
23030-10000-07857
Plan Check / Job No.
G23LA00163
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
EPLAN: PROPOSED REMEDIAL SLOPE REPAIR WITH PIPE AND BOARD PER SOILS ENGINEER RECOMMENDATIONS. CUT = 25 CY. FILL = 35 CY IMPORT = 10 CY
Permit Issued
Issued on 5/13/2024
Issuing Office
Current Status
Permit Finaled on 9/20/2024

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/10/2024 DAN RYAN EVANGELISTA
Corrections Issued 1/10/2024 DAN RYAN EVANGELISTA
Quality Review Completed 1/10/2024 DAN RYAN EVANGELISTA
Applicant returned to address corrections 1/30/2024 DAN RYAN EVANGELISTA
Plan Check Approved 4/17/2024 DAN RYAN EVANGELISTA
Issued 5/13/2024 APPLICANT
Permit Finaled 9/19/2024 JONATHAN HOM

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/26/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: NA53260       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 5/17/2024 Corrections Issued JONATHAN HOM
Bottom/Toe 5/20/2024 Corrections Issued JONATHAN HOM
Bottom/Toe 5/29/2024 Partial Approval JONATHAN HOM
Excavation 5/29/2024 Partial Inspection JONATHAN HOM
Initial Grading 5/29/2024 Partial Inspection JONATHAN HOM
Fill/Backfill 6/10/2024 Partial Approval MICHAEL TEMPLE
Sub-Drain 6/10/2024 Partial Approval MICHAEL TEMPLE
Bottom/Toe 8/19/2024 Corrections Issued JONATHAN HOM
Fill/Backfill 8/19/2024 Partial Inspection JONATHAN HOM
Sub-Drain 8/19/2024 Partial Inspection JONATHAN HOM
Fill/Backfill 8/22/2024 Approved JONATHAN HOM
Approved Compaction Report 9/17/2024 Approved JONATHAN HOM
Bottom/Toe 9/19/2024 Approved JONATHAN HOM
Final 9/19/2024 Permit Finaled JONATHAN HOM
Rough 9/19/2024 Approved JONATHAN HOM