9314 W LLOYDCREST DR 90210
Certificate Information: 9314 W LLOYDCREST DR 90210
- Application / Permit
- 23030-10000-07088
- Plan Check / Job No.
- G23LA00148
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Removal all loose spoils down to the original slope surface, removal of one row of railroad ties and backfill of all non-permitted excavations back to 2H:1V for slope stabilization. Cut 2CY, Fill 2CY
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Current Status
- Issued on 5/29/2024
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2023 | ALAN DANG |
| Corrections Issued | 12/13/2023 | ALAN DANG |
| Applicant returned to address corrections | 4/29/2024 | ALAN DANG |
| Applicant returned to address corrections | 5/17/2024 | ALAN DANG |
| Plan Check Approved | 5/24/2024 | ALAN DANG |
| Issued | 5/29/2024 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 1/4/2024 | DANIEL CORONADO |
| ZI | Cleared | 1/4/2024 | DANIEL CORONADO |
| Work Adjacent to Public Way | Cleared | 1/19/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 5/17/2024 | ALAN DANG |
Contact Information
| Contractor | Qualitystruct Construction Inc; Lic. No.: 1013844-A | 6042 FAIR AVENUE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Djoneva,, Diana Ivanova; Lic. No.: C73805 | 3241 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/18/2024 | Corrections Issued | ALEXANDER HELFER |
| Special/Order Compliance | 6/18/2024 | Partial Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 6/26/2024 | Corrections Issued | ALEXANDER HELFER |
| Bottom/Toe | 7/12/2024 | Partial Inspection | ALEXANDER HELFER |
| Final | 7/12/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 7/12/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 9/9/2024 | Partial Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 2/12/2025 | Partial Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 2/12/2025 | Partial Inspection | LANNY MERRICK |
| Special/Order Compliance | 2/12/2025 | Partial Inspection | MICHAEL TEMPLE |
| Special/Order Compliance | 1/9/2026 | Partial Inspection | MICHAEL TEMPLE |