10304 S FIGUEROA ST 90003
Certificate Information: 10304 S FIGUEROA ST 90003
- Application / Permit
- 23030-10000-06858
- Plan Check / Job No.
- B22LA11213
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ePLAN. GRADING FOR NEW APARTMENT.
- Permit Issued
- Issued on 6/5/2025
- Issuing Office
- Current Status
- Issued on 6/5/2025
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | KEVIN MORALES |
| Corrections Issued | 6/21/2022 | KEVIN MORALES |
| Quality Review Completed | 6/21/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/31/2022 | KEVIN MORALES |
| Plan Check Approved | 4/9/2025 | KEVIN MORALES |
| Issued | 6/5/2025 | APPLICANT |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 11/28/2023 | CALOSHA APPROVED |
| Community Plan Implem. Overlay | Cleared | 11/29/2023 | MANERI ROMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 8/22/2025 | Corrections Issued | JONATHAN HOM |
| Deputy Grading | 8/22/2025 | Conditional Approval | JONATHAN HOM |
| Bottom/Toe | 8/25/2025 | Partial Approval | JONATHAN HOM |
| Initial Grading | 8/25/2025 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 8/26/2025 | Approved | JONATHAN HOM |
| Excavation | 8/26/2025 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 8/26/2025 | Partial Inspection | JONATHAN HOM |
| Fill/Backfill | 8/27/2025 | Approved | JONATHAN HOM |
| Deputy Grading | 8/28/2025 | Approved | JONATHAN HOM |
| Bottom/Toe | 9/2/2025 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 9/6/2025 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 9/8/2025 | Partial Approval | JONATHAN HOM |
| Approved Compaction Report | 9/16/2025 | Approved | RUSSELL BONVOULOIR |