522-522 1/2 W 75TH ST 90044
Certificate Information: 522-522 1/2 W 75TH ST 90044
- Application / Permit
- 23030-10000-06339
- Plan Check / Job No.
- B23LA11074
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING PERMIT FOR R&R
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/19/2025
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | VIVIAN LAO |
| Corrections Issued | 7/7/2023 | VIVIAN LAO |
| Quality Review Completed | 7/14/2023 | KEN GILL |
| Building Plans Picked Up | 7/17/2023 | APPLICANT |
| Plan Check Approved | 10/11/2023 | VIVIAN LAO |
| Issued | 2/28/2024 | APPLICANT |
| Permit Finaled | 2/18/2025 | JONATHAN HOM |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | PO BOX 39459 DOWNEY, CA 90241 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 4/19/2024 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 4/24/2024 | Partial Approval | JONATHAN HOM |
| Approved Compaction Report | 6/3/2024 | Approved | JONATHAN HOM |
| Bottom/Toe | 2/18/2025 | Approved | JONATHAN HOM |
| Final | 2/18/2025 | Permit Finaled | JONATHAN HOM |
| Rough | 2/18/2025 | Approved | JONATHAN HOM |