10619 W CHALON ROAD 90077
Certificate Information: 10619 W CHALON ROAD 90077
- Application / Permit
- 23030-10000-06049
- Plan Check / Job No.
- G23LA00127
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- REMOVE UNPERMITTED FILL AND RESTORE TO ORIGINAL GRADE PER OTC B0112912-954; CUT = 1,350 CY; EXPORT = 1,755 CY. **HAUL ROUTE REQUIRED** BOARD FILE 240039 APPROVED FOR A MAXIMUM EXPORT OF 1,755 CUBIC YARDS
- Permit Issued
- Issued on 11/9/2024
- Issuing Office
- Current Status
- Permit Finaled on 3/6/2025
Permit Application Status History
| Submitted | 9/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | DAN RYAN EVANGELISTA |
| Corrections Issued | 10/12/2023 | DAN RYAN EVANGELISTA |
| Applicant returned to address corrections | 11/22/2023 | ROCIO DURAN |
| Applicant returned to address corrections | 11/1/2024 | ROCIO DURAN |
| Plan Check Approved | 11/8/2024 | ROCIO DURAN |
| Issued | 11/9/2024 | APPLICANT |
| Permit Finaled | 3/5/2025 | MATTHEW JENKINS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/4/2024 | JAZMIN ROQUE |
| Excavation more than 5-ft deep | Cleared | 9/13/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 9/13/2024 | DAN RYAN EVANGELISTA |
| Haul Route | Cleared | 11/5/2024 | ALAN MORELOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Haro,, Ruben; Lic. No.: GE2990 | 899 PIERCE COURT THOUSAND OAKS, CA 91360 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C93123 | 889 PIERCE COURT, SUITE 101 THOUSAND OAKS, CA 91360 |
| Geologist | Holt,, Jacob William; Lic. No.: EG2282 | 5158 COCHRAN ST SIMI VALLEY, CA 93063 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 11/13/2024 | Corrections Issued | JOHNNY MIRANDA |
| Deputy Grading | 11/20/2024 | Conditional Approval | JOHNNY MIRANDA |
| Excavation | 11/20/2024 | Corrections Issued | JOHNNY MIRANDA |
| Deputy Grading | 11/21/2024 | No Access for Inspection | VASIL MIHALEV |
| Deputy Grading | 11/22/2024 | Corrections Issued | JOHNNY MIRANDA |
| Excavation | 11/22/2024 | Corrections Issued | JOHNNY MIRANDA |
| Special/Order Compliance | 12/3/2024 | Partial Inspection | JOHNNY MIRANDA |
| Deputy Grading | 12/6/2024 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 12/9/2024 | Approved | VASIL MIHALEV |
| Deputy Grading | 12/11/2024 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 12/12/2024 | Conditional Approval | ALEXANDER HELFER |
| Bottom/Toe | 12/19/2024 | Approved | JOHNNY MIRANDA |
| Final | 12/19/2024 | Corrections Issued | JOHNNY MIRANDA |
| Order to Comply | 12/19/2024 | OTC Issued | JOHNNY MIRANDA |
| Rough | 12/19/2024 | Approved | JOHNNY MIRANDA |
| Final | 1/15/2025 | Partial Inspection | MATTHEW JENKINS |
| Final | 1/23/2025 | Corrections Issued | MATTHEW JENKINS |
| Final | 2/12/2025 | Corrections Issued | MATTHEW JENKINS |
| Final | 3/5/2025 | Permit Finaled | MATTHEW JENKINS |