1830 N DILLON ST 90026

Certificate Information: 1830 N DILLON ST 90026

Application / Permit
23030-10000-05900
Plan Check / Job No.
B23LA17669
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW CONSTRUCTION OF (2) NEW ACCESSORY BUILDINGS AND NEW POOL AND HOT TUB; TOTAL EXPORT = 44 CY.
Permit Issued
Issued on 4/15/2024
Issuing Office
Metro
Current Status
Issued on 4/15/2024

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 NGHI SU
Corrections Issued 10/5/2023 NGHI SU
Quality Review Completed 10/6/2023 KEN GILL
Plan Check Approved 11/20/2023 NGHI SU
Issued 4/15/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/13/2023 OSCAR CASTRO
Construction within easement Cleared 10/13/2023 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 10/18/2023 JUSTIN BICOL
Roof/Waste drainage to street Cleared 10/18/2023 JUSTIN BICOL
Grading Pre-Inspection Cleared 11/20/2023 NGHI SU

Contact Information

Architect Neubert,, Aaron Douglas; Lic. No.: C29005 3052 BERKELEY CIRCLE      LOS ANGELES, CA 90026
Contractor Dbgc Inc; Lic. No.: 1009448-B 4000 SUNNYSLOPE AVE      SHERMAN OAKS, CA 91423
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Shirley,, Peter; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/23/2024 Approved RUSSELL BONVOULOIR
Excavation 10/20/2025 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 3/3/2026 Not Ready for Inspection ROBERT PINA
Final 3/3/2026 Corrections Issued ROBERT PINA
Rough 3/3/2026 Not Ready for Inspection ROBERT PINA
Bottom/Toe 6/3/2026 Not Ready for Inspection RAMAZANALI ALMASI
Final 6/3/2026 Not Ready for Inspection RAMAZANALI ALMASI
Rough 6/3/2026 Not Ready for Inspection RAMAZANALI ALMASI