110 N MAPLETON DR 90077
Certificate Information: 110 N MAPLETON DR 90077
- Application / Permit
- 23030-10000-05862
- Plan Check / Job No.
- B22LA24589
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePlan SITE GRADING FOR NEW ALQ AND RT WALL
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- Current Status
- Issued on 10/30/2023
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/11/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 9/19/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/24/2023 | MAHNAZ NOURHASHEMI |
| Issued | 10/30/2023 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/8/2023 | Approved | RUSSELL BONVOULOIR |
| Deputy Grading | 12/12/2023 | Partial Approval | CHARLES POWELL |
| Deputy Grading | 12/14/2023 | Partial Approval | CHARLES POWELL |
| Excavation | 1/16/2024 | Partial Approval | MATTHEW JENKINS |
| Fill/Backfill | 1/16/2024 | Partial Inspection | MATTHEW JENKINS |
| Rough | 1/24/2024 | Corrections Issued | AL GAMBLE |
| Approved Compaction Report | 3/6/2024 | Not Ready for Inspection | JOHNNY MIRANDA |
| Approved Compaction Report | 3/8/2024 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 3/22/2024 | Partial Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 3/22/2024 | Partial Approval | AL GAMBLE |
| Special/Order Compliance | 5/20/2025 | Not Ready for Inspection | MATTHEW JENKINS |