7995 W BRIAR SUMMIT DR 90046

Certificate Information: 7995 W BRIAR SUMMIT DR 90046

Application / Permit
23030-10000-05801
Plan Check / Job No.
B23LA15681
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
proposed site grading for proposed garage expansion and new proposed entry way
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
Permit Finaled on 8/25/2025

Permit Application Status History

Submitted 8/23/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 MINA HABIB
Corrections Issued 9/18/2023 MINA HABIB
Quality Review Completed 9/19/2023 RODOLFO ARIAS
Applicant returned to address corrections 10/17/2023 MINA HABIB
Applicant returned to address corrections 11/29/2023 MINA HABIB
Applicant returned to address corrections 12/6/2023 MINA HABIB
Applicant returned to address corrections 1/26/2024 MINA HABIB
Applicant returned to address corrections 2/5/2024 MINA HABIB
Applicant returned to address corrections 2/6/2024 MINA HABIB
Applicant returned to address corrections 2/15/2024 MINA HABIB
Applicant returned to address corrections 2/21/2024 MINA HABIB
Applicant returned to address corrections 4/3/2024 MINA HABIB
Applicant returned to address corrections 4/4/2024 MINA HABIB
Applicant returned to address corrections 4/5/2024 MINA HABIB
Applicant returned to address corrections 4/9/2024 MINA HABIB
Applicant returned to address corrections 4/25/2024 MINA HABIB
Applicant returned to address corrections 5/20/2024 MINA HABIB
Applicant returned to address corrections 5/21/2024 MINA HABIB
Applicant returned to address corrections 6/3/2024 MINA HABIB
Applicant returned to address corrections 6/4/2024 MINA HABIB
Plan Check Approved 6/5/2024 MINA HABIB
Issued 11/7/2024 APPLICANT
Permit Finaled 8/25/2025 ROBERT PINA

Permit Application Clearance Information

Certificate of Compliance Cleared 12/13/2023 SPENCER WEJROWSKI
Miscellaneous Cleared 12/13/2023 SPENCER WEJROWSKI
Specific Plan Cleared 1/17/2024 TIFFANY CORRALES
Specific Plan Cleared 1/17/2024 TIFFANY CORRALES
Eng Process Fee Ord 176,300 Cleared 2/9/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 2/9/2024 JEANIE LAM
Construction near power lines Cleared 2/15/2024 WALTER RAMIREZ
Construction within easement Cleared 2/15/2024 WALTER RAMIREZ
Work Adjacent to Public Way Cleared 3/5/2024 LARRY LEE
Grading Pre-Inspection Cleared 4/9/2024 MINA HABIB
Excavation more than 5-ft deep Cleared 6/3/2024 CALOSHA APPROVED

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Aparicio,, Daniel Gonzalo; Lic. No.: C92121 19332 AVENIDA DEL SOL      WALNUT, CA 91789
Engineer Jardine, Prouty, Kyle Addison; Lic. No.: C95048 2239 STATE AVE   UNIT B    COSTA MESA, CA 92627
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025
Geologist Nguyen,, An; Lic. No.: EG2468 5913 SATURN STREET      LOS ANGELES, CA 90035

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 12/31/2024 Approved ALEXANDER HELFER
Sub-Drain 1/27/2025 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 3/14/2025 Approved ALEXANDER HELFER
Approved Compaction Report 7/16/2025 Approved RUSSELL BONVOULOIR
Bottom/Toe 8/25/2025 Approved ROBERT PINA
Final 8/25/2025 Permit Finaled ROBERT PINA
Initial Grading 8/25/2025 Approved ROBERT PINA
Rough 8/25/2025 Approved ROBERT PINA