1801 E 50TH ST 90058
Certificate Information: 1801 E 50TH ST 90058
- Application / Permit
- 23030-10000-05747
- Plan Check / Job No.
- B22LA25869
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for proposed Warehouse building: Removal and Recompaction for building under 22010-10000-06328
- Permit Issued
- Issued on 12/8/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/2/2024
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 2/10/2023 | APPLICANT |
| Corrections Issued | 2/23/2023 | HERNAN ARREOLA |
| Quality Review Completed | 2/24/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 2/27/2023 | APPLICANT |
| Applicant returned to address corrections | 4/12/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/17/2023 | HERNAN ARREOLA |
| Plan Check Approved | 12/4/2023 | HERNAN ARREOLA |
| Issued | 12/8/2023 | APPLICANT |
| Permit Finaled | 9/30/2024 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 9/14/2023 | HELEN JADALI |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | JEANIE LAM |
| Work Adjacent to Public Way | Cleared | 12/1/2023 | JOSE RODRIGUEZ |
| Miscellaneous | Cleared | 12/4/2023 | HERNAN ARREOLA |
Contact Information
| Contractor | Mac Construction Builders Inc; Lic. No.: 1065329-B | 4100 WILSHIRE BLVD #403 LOS ANGELES, CA 90010 |
| Engineer | Kim,, Steve; Lic. No.: C88484 | 7003 VINING STREET CHINO, CA 91710 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/12/2023 | Corrections Issued | JONATHAN HOM |
| Initial Grading | 12/13/2023 | Partial Inspection | JONATHAN HOM |
| Deputy Grading | 12/14/2023 | Approved | JONATHAN HOM |
| Bottom/Toe | 12/18/2023 | Partial Approval | JONATHAN HOM |
| Excavation | 12/18/2023 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 1/9/2024 | Approved | JONATHAN HOM |
| Bottom/Toe | 8/12/2024 | Approved | JONATHAN HOM |
| Excavation | 8/12/2024 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 8/12/2024 | Partial Inspection | JONATHAN HOM |
| Final | 9/30/2024 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 9/30/2024 | Approved | RUSSELL BONVOULOIR |