3871 S GRAND VIEW BLVD 90066
Certificate Information: 3871 S GRAND VIEW BLVD 90066
- Application / Permit
- 23030-10000-05645
- Plan Check / Job No.
- B23LA16350
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- EPLAN PROPOSED GRADING FOR NEW STORAGE BUILDING. 2 OF 2
- Permit Issued
- Issued on 9/25/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/10/2026
Permit Application Status History
| Submitted | 9/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | MICHAEL LOPEZ |
| Corrections Issued | 9/20/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 9/26/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 6/26/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/2/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/5/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/29/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 9/24/2024 | MICHAEL LOPEZ |
| Issued | 9/25/2024 | APPLICANT |
| Permit Finaled | 4/9/2026 | JOHNNY MIRANDA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Jordan,, Bruce Didrik; Lic. No.: C12923 | 131 CALLE IGLESIA SUITE 100 SAN CLEMENTE, CA 92672 |
| Contractor | L T Building Corp; Lic. No.: 1063419-B | , |
| Engineer | Elder,, John; Lic. No.: S6534 | 5181 S EMERALD PL CHANDLER, AZ 85249 |
| Engineer | Soltis,, Paul Christopher; Lic. No.: GE2606 | 5732 LEMON AVE CYPRESS, CA 90630 |
| Geologist | Browning,, Jonathan Anton; Lic. No.: EG2615 | 228 CANYON CREEK WAY OCEANSIDE, CA 92057 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/10/2024 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 10/17/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 10/17/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 10/23/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 10/24/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 10/25/2024 | Approved | AL GAMBLE |
| Deputy Grading | 10/29/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 10/30/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 11/1/2024 | Approved | AL GAMBLE |
| Deputy Grading | 11/4/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 11/5/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 11/6/2024 | Conditional Approval | MATTHEW JENKINS |
| Approved Compaction Report | 11/26/2024 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 12/4/2024 | Approved | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/9/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 12/10/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/10/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 12/11/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/11/2024 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 12/12/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 12/12/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 12/13/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/13/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/16/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 12/17/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/17/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/18/2024 | Conditional Approval | MATTHEW JENKINS |
| Deputy Other (see comments) | 12/20/2024 | Approved | VASIL MIHALEV |
| Fill/Backfill | 1/16/2025 | Partial Approval | JOHNNY MIRANDA |
| Fill/Backfill | 1/23/2025 | Partial Inspection | AL GAMBLE |
| Fill/Backfill | 4/29/2025 | Partial Inspection | AL GAMBLE |
| Excavation | 6/24/2025 | Not Ready for Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 8/5/2025 | Partial Inspection | JONATHAN HOM |
| Excavation | 8/5/2025 | Partial Inspection | JONATHAN HOM |
| Deputy Grading | 8/12/2025 | Approved | AL GAMBLE |
| Deputy Grading | 8/14/2025 | Approved | AL GAMBLE |
| Fill/Backfill | 8/14/2025 | Not Ready for Inspection | AL GAMBLE |
| Rough | 8/14/2025 | Partial Approval | AL GAMBLE |
| Deputy Grading | 8/15/2025 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 8/21/2025 | Approved | AL GAMBLE |
| Fill/Backfill | 8/21/2025 | Partial Approval | AL GAMBLE |
| Sub-Drain | 8/21/2025 | Partial Inspection | AL GAMBLE |
| Deputy Grading | 8/26/2025 | Conditional Approval | LANNY MERRICK |
| Fill/Backfill | 8/26/2025 | Partial Inspection | LANNY MERRICK |
| Drainage Devices/Catch Basin | 9/12/2025 | Partial Approval | AL GAMBLE |
| Drainage Devices/Catch Basin | 9/16/2025 | Partial Approval | AL GAMBLE |
| Sub-Drain | 9/25/2025 | Approved | LANNY MERRICK |
| Deputy Grading | 9/30/2025 | Approved | AL GAMBLE |
| Irrigation/Landscape | 10/15/2025 | Partial Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 10/23/2025 | Partial Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 11/18/2025 | Approved | LANNY MERRICK |
| Fill/Backfill | 12/3/2025 | No Access for Inspection | ROBERT PINA |
| Rough | 12/3/2025 | No Access for Inspection | ROBERT PINA |
| Fill/Backfill | 12/9/2025 | Partial Approval | ROBERT PINA |
| Rough | 12/9/2025 | Partial Approval | ROBERT PINA |
| Drainage Devices/Catch Basin | 1/28/2026 | Approved | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 2/26/2026 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Grading | 3/3/2026 | Conditional Approval | JOHNNY MIRANDA |
| Approved Compaction Report | 4/9/2026 | Approved | JOHNNY MIRANDA |
| Bottom/Toe | 4/9/2026 | Approved | JOHNNY MIRANDA |
| Final | 4/9/2026 | Permit Finaled | JOHNNY MIRANDA |
| Rough | 4/9/2026 | Approved | JOHNNY MIRANDA |