4439 N CALHOUN AVE 91423

Certificate Information: 4439 N CALHOUN AVE 91423

Application / Permit
23030-10000-05624
Plan Check / Job No.
B23LA16756
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
9/6 eplan R&R for (n) ADU at rear.
Permit Issued
Issued on 9/20/2023
Issuing Office
Current Status
Permit Finaled on 5/2/2025

Permit Application Status History

Submitted 9/8/2023 APPLICANT
Assigned to Plan Check Engineer 9/8/2023 ADRIANA LOPEZ
Plan Check Approved 9/19/2023 ADRIANA LOPEZ
Issued 9/20/2023 APPLICANT
Permit Finaled 5/2/2025 MANUEL TEJADA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Approved Compaction Report 10/16/2023 Not Ready for Inspection MANUEL TEJADA
Bottom/Toe 10/16/2023 Corrections Issued MANUEL TEJADA
Fill/Backfill 10/16/2023 Not Ready for Inspection MANUEL TEJADA
Final 10/16/2023 Not Ready for Inspection MANUEL TEJADA
Rough 10/16/2023 Not Ready for Inspection MANUEL TEJADA
Approved Compaction Report 11/9/2023 Corrections Issued MANUEL TEJADA
Bottom/Toe 1/6/2025 Corrections Issued MANUEL TEJADA
Final 1/6/2025 Corrections Issued MANUEL TEJADA
Rough 1/6/2025 Approved MANUEL TEJADA
Bottom/Toe 1/13/2025 Not Ready for Inspection MANUEL TEJADA
Final 1/13/2025 Not Ready for Inspection MANUEL TEJADA
Approved Compaction Report 2/25/2025 Corrections Issued MANUEL TEJADA
Bottom/Toe 3/26/2025 Partial Inspection MANUEL TEJADA
Final 3/26/2025 Partial Inspection MANUEL TEJADA
Approved Compaction Report 5/2/2025 Approved MANUEL TEJADA
Bottom/Toe 5/2/2025 Approved MANUEL TEJADA
Final 5/2/2025 Permit Finaled MANUEL TEJADA