4000 E CHEVY CHASE DR 90039

Certificate Information: 4000 E CHEVY CHASE DR 90039

Application / Permit
23030-10000-05163
Plan Check / Job No.
B22LA13705
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
grading for site work
Permit Issued
Issued on 8/22/2023
Issuing Office
Metro
Current Status
Permit Finaled on 2/25/2026

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 ARSALAN SHABESTARI
Corrections Issued 8/11/2022 ARSALAN SHABESTARI
Quality Review Completed 8/18/2022 KEN GILL
Building Plans Picked Up 10/3/2022 APPLICANT
Disabled Access Plans Picked Up 10/3/2022 APPLICANT
Plan Check Approved 8/17/2023 ARSALAN SHABESTARI
Issued 8/22/2023 APPLICANT
Permit Finaled 2/24/2026 RAMAZANALI ALMASI

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Burner Construction Corp; Lic. No.: 1041968-B PO BOX 2535      CHINO, CA 91708

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/13/2024 Approved ALEXANDER HELFER
Fill/Backfill 3/29/2024 Not Ready for Inspection JONATHAN HOM
Rough 4/1/2024 Not Ready for Inspection LANNY MERRICK
Fill/Backfill 4/3/2024 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 4/24/2024 Partial Approval RUSSELL BONVOULOIR
Excavation 5/29/2024 Partial Inspection RUSSELL BONVOULOIR
Rough 5/29/2024 Partial Approval RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 6/27/2024 Partial Inspection RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 9/18/2025 Partial Approval RUSSELL BONVOULOIR
Irrigation/Landscape 9/18/2025 Partial Approval RUSSELL BONVOULOIR
Rough 9/18/2025 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 9/18/2025 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 12/26/2025 Partial Approval RAMAZANALI ALMASI
Irrigation/Landscape 2/2/2026 Corrections Issued ROBERT PINA
Approved Compaction Report 2/19/2026 Approved RAMAZANALI ALMASI
Bottom/Toe 2/24/2026 Approved RAMAZANALI ALMASI
Final 2/24/2026 Permit Finaled RAMAZANALI ALMASI