209 S 5TH AVE 90291
Certificate Information: 209 S 5TH AVE 90291
- Application / Permit
- 23030-10000-04599
- Plan Check / Job No.
- B23LA13714
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR RETAINING WALLS
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Current Status
- Issued on 10/4/2024
Permit Application Status History
| Submitted | 7/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 8/16/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/18/2023 | KEN GILL |
| Building Plans Picked Up | 8/23/2023 | APPLICANT |
| Plan Check Approved | 10/3/2024 | MARCELA FRANQUEZ |
| Issued | 10/4/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/30/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2023 | WALLIE JONG |
| Coastal Zone | Cleared | 11/28/2023 | DAVID URITA |
| Miscellaneous | Cleared | 11/28/2023 | DAVID URITA |
| Miscellaneous | Cleared | 11/28/2023 | DAVID URITA |
| Miscellaneous | Cleared | 11/28/2023 | DAVID URITA |
| Specific Plan | Cleared | 11/28/2023 | DAVID URITA |
| ZA Case | Cleared | 11/28/2023 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 10/8/2024 | Not Ready for Inspection | AL GAMBLE |
| Initial Grading | 10/8/2024 | Not Ready for Inspection | AL GAMBLE |
| Sub-Drain | 2/6/2025 | Partial Approval | JOHNNY MIRANDA |
| Fill/Backfill | 2/21/2025 | Partial Inspection | AL GAMBLE |
| Sub-Drain | 2/21/2025 | Partial Approval | AL GAMBLE |
| Sub-Drain | 2/27/2025 | Partial Approval | AL GAMBLE |
| Approved Compaction Report | 3/27/2025 | Partial Inspection | AL GAMBLE |
| Approved Compaction Report | 4/18/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 5/8/2025 | Approved | LANNY MERRICK |
| Bottom/Toe | 6/17/2025 | Approved | LANNY MERRICK |
| Final | 6/17/2025 | Not Ready for Inspection | LANNY MERRICK |
| Rough | 6/17/2025 | Approved | LANNY MERRICK |
| Final | 7/23/2025 | Not Ready for Inspection | MATTHEW JENKINS |