2990 N SILVER LAKE BLVD 90039

Certificate Information: 2990 N SILVER LAKE BLVD 90039

Application / Permit
23030-10000-04574
Plan Check / Job No.
B23LA13639
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
grading for access pit 5
Permit Issued
Issued on 12/11/2023
Issuing Office
Metro
Current Status
Permit Finaled on 10/14/2025

Permit Application Status History

Submitted 7/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 ARSALAN SHABESTARI
Corrections Issued 8/24/2023 ARSALAN SHABESTARI
Quality Review Completed 9/1/2023 KEN GILL
Building Plans Picked Up 9/5/2023 APPLICANT
Applicant returned to address corrections 11/15/2023 ARSALAN SHABESTARI
Plan Check Approved 12/7/2023 ARSALAN SHABESTARI
Issued 12/11/2023 APPLICANT
Permit Finaled 10/14/2025 RAMAZANALI ALMASI

Permit Application Clearance Information

City owned building/parcel Cleared 10/25/2023 ARSALAN SHABESTARI
"Q" conditions Cleared 10/26/2023 MAYELA VILLA
Tract Map conditions Cleared 10/26/2023 MAYELA VILLA
Tract Map conditions Cleared 10/26/2023 MAYELA VILLA
Tract Map conditions Cleared 10/26/2023 MAYELA VILLA
ZI Cleared 10/26/2023 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 11/14/2023 STEVE MELGAR
Sewer availability Cleared 11/14/2023 STEVE MELGAR
Excavation more than 5-ft deep Cleared 11/15/2023 CALOSHA APPROVED

Contact Information

Contractor J R Pipeline Co Inc; Lic. No.: 435130-A 1530 NANDINA AVENUE      PERRIS, CA 92571

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 2/12/2024 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 2/21/2024 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 2/23/2024 Conditional Approval RUSSELL BONVOULOIR
Bottom/Toe 7/1/2025 Approved RAMAZANALI ALMASI
Deputy Grading 7/7/2025 Conditional Approval RAMAZANALI ALMASI
Deputy Grading 7/8/2025 No Result Entered ROBERT HUGHES
Final 8/12/2025 Not Ready for Inspection RAMAZANALI ALMASI
Rough 8/12/2025 Approved RAMAZANALI ALMASI
Final 10/14/2025 Permit Finaled RAMAZANALI ALMASI