6736 W FOOTHILL BLVD 91042

Certificate Information: 6736 W FOOTHILL BLVD 91042

Application / Permit
23030-10000-03600
Plan Check / Job No.
B23VN03301
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
(N) GRADING FOR DRIVE TRHU STARBUCKS BUILDING
Permit Issued
Issued on 2/23/2024
Issuing Office
Current Status
Permit Finaled on 3/10/2025

Permit Application Status History

Submitted 3/17/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 SERGIO GUTIERREZ
Corrections Issued 3/29/2023 SERGIO GUTIERREZ
Quality Review Completed 3/31/2023 RODOLFO ARIAS
Applicant returned to address corrections 5/26/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 7/5/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 8/22/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 2/9/2024 SERGIO GUTIERREZ
Plan Check Approved 2/23/2024 SERGIO GUTIERREZ
Issued 2/23/2024 APPLICANT
Permit Finaled 3/7/2025 MANUEL TEJADA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Sipan Contruction Co.; Lic. No.: 676103-B 3200 LA CRESCENTA AVE SUITE_B      GLENDALE, CA 91208

Inspector Information

BRIAN MILLER, (818) 374-4359 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 3/20/2024 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 3/28/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/28/2024 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Protected Tree Letter 4/8/2024 Corrections Issued CHARLES POWELL
Special/Order Compliance 4/12/2024 Partial Approval MANUEL TEJADA
Excavation 4/17/2024 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 5/2/2024 Partial Approval CHARLES POWELL
Bottom/Toe 6/11/2024 Not Ready for Inspection CHARLES POWELL
Drainage Devices/Catch Basin 6/14/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 6/27/2024 Approved GERMAN RODRIGUEZ MENDOZA
Sub-Drain 7/2/2024 Partial Approval CHARLES POWELL
Bottom/Toe 10/30/2024 Conditional Approval LANNY MERRICK
Approved Compaction Report 2/3/2025 Approved MANUEL TEJADA
Bottom/Toe 3/7/2025 Approved MANUEL TEJADA
Final 3/7/2025 Permit Finaled MANUEL TEJADA
Rough 3/7/2025 Approved MANUEL TEJADA