4901 W ROMAINE ST 90029
Certificate Information: 4901 W ROMAINE ST 90029
- Application / Permit
- 23030-10000-03081
- Plan Check / Job No.
- B23LA06586
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading: Excavation for new retaining walls 2 of 2
- Permit Issued
- Issued on 7/8/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/22/2026
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | TSE MING HUANG |
| Corrections Issued | 5/11/2023 | TSE MING HUANG |
| Quality Review Completed | 5/16/2023 | EUGENE BARBEAU |
| Plan Check Approved | 2/6/2024 | TSE MING HUANG |
| Issued | 7/8/2024 | APPLICANT |
| Permit Finaled | 1/22/2026 | RAMAZANALI ALMASI |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 11/14/2023 | SHAHIN KHAZEY |
| Encroachment in public way | Cleared | 11/16/2023 | KATHERINE MENDOZA |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2023 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 12/11/2023 | CELINA MORENO |
Contact Information
| Contractor | H T A Construction & Development; Lic. No.: 1044038-B | , |
| Contractor | Hta Construction & Development; Lic. No.: 1044038-B | , |
| Engineer | Jitechian,, Ara; Lic. No.: C54893 | 9433 VIA PATRICIA BURBANK, CA 91504 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sub-Drain | 10/2/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 10/3/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Sub-Drain | 11/1/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 3/5/2025 | Approved | LANNY MERRICK |
| Final | 3/5/2025 | Not Ready for Inspection | LANNY MERRICK |
| Rough | 3/5/2025 | Approved | LANNY MERRICK |
| Approved Compaction Report | 1/9/2026 | Approved | RAMAZANALI ALMASI |
| Final | 1/21/2026 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 1/22/2026 | Permit Finaled | RAMAZANALI ALMASI |