8880 W EVANVIEW DR 90069
Certificate Information: 8880 W EVANVIEW DR 90069
- Application / Permit
- 23030-10000-03080
- Plan Check / Job No.
- B23LA08851
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- EPLAN: Grading permit
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Metro
- Current Status
- Issued on 9/19/2023
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | JAD BASMA |
| Corrections Issued | 6/9/2023 | JAD BASMA |
| Quality Review Completed | 6/16/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 8/30/2023 | JAD BASMA |
| No Progress | 8/30/2023 | JAD BASMA |
| Plan Check Approved | 8/30/2023 | JAD BASMA |
| Plan Check Approved | 9/19/2023 | JAD BASMA |
| Issued | 9/19/2023 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/15/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 8/15/2023 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Contractor | Renaissance Construction Group Inc; Lic. No.: 1019679-A | 22151 VENTURA BLVD 200 WOODLAND HILLS, CA 91364 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/25/2023 | Not Ready for Inspection | ALEXANDER HELFER |
| Initial Grading | 9/26/2023 | Corrections Issued | ALEXANDER HELFER |
| Special/Order Compliance | 12/18/2023 | Order to Comply Issued | ALEXANDER HELFER |
| Special/Order Compliance | 12/22/2023 | Order to Comply Issued | ALEXANDER HELFER |
| Special/Order Compliance | 12/27/2023 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 1/5/2024 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 1/9/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 1/12/2024 | Partial Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 1/23/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Special/Order Compliance | 2/23/2024 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 3/19/2024 | Corrections Issued | ALEXANDER HELFER |
| Special/Order Compliance | 3/22/2024 | Corrections Issued | ALEXANDER HELFER |
| Special/Order Compliance | 4/8/2024 | Partial Approval | ALEXANDER HELFER |
| Special/Order Compliance | 4/9/2024 | No Access for Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 4/25/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Special/Order Compliance | 6/5/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Special/Order Compliance | 9/4/2024 | Approved | ALEXANDER HELFER |
| Special/Order Compliance | 10/1/2024 | Corrections Issued | ALEXANDER HELFER |
| Initial Grading | 11/15/2024 | Approved | ALEXANDER HELFER |
| Sub-Drain | 1/3/2025 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 2/25/2025 | Approved | ALEXANDER HELFER |
| Sub-Drain | 4/29/2025 | Partial Approval | ROBERT PINA |
| Special/Order Compliance | 7/24/2025 | Approved | ROBERT PINA |
| Sub-Drain | 1/28/2026 | Partial Approval | ROBERT PINA |