6850 N VINELAND AVE 91605
Certificate Information: 6850 N VINELAND AVE 91605
- Application / Permit
- 23030-10000-02799
- Plan Check / Job No.
- B23VN04985
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- EPLAN PROPOSED GRADING FOR NEW STORAGE BUILDING. 2 OF 2
- Permit Issued
- Issued on 9/12/2024
- Issuing Office
- Current Status
- Issued on 9/12/2024
Permit Application Status History
| Submitted | 4/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | MICHAEL LOPEZ |
| Corrections Issued | 5/11/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 5/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/2/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/1/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/19/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 9/4/2024 | MICHAEL LOPEZ |
| Issued | 9/12/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Jordan,, Bruce Didrik; Lic. No.: C12923 | 131 CALLE IGLESIA SUITE 100 SAN CLEMENTE, CA 92672 |
| Contractor | L T Building Corp; Lic. No.: 1063419-B | , |
| Engineer | Elder,, John; Lic. No.: S6534 | 5181 S EMERALD PL CHANDLER, AZ 85249 |
| Engineer | Mensen,, Jodi Lindsey; Lic. No.: C79693 | 1748 ORANGEWOOD AVE UPLAND, CA 91784 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/19/2024 | Corrections Issued | MANUEL TEJADA |
| Initial Grading | 9/26/2024 | Approved | MANUEL TEJADA |
| Deputy Grading | 10/1/2024 | No Access for Inspection | MANUEL TEJADA |
| Bottom/Toe | 10/3/2024 | Conditional Approval | MANUEL TEJADA |
| Deputy Grading | 10/3/2024 | Approved | MANUEL TEJADA |
| Excavation | 10/7/2024 | Corrections Issued | MANUEL TEJADA |
| Bottom/Toe | 10/9/2024 | Partial Approval | MANUEL TEJADA |
| Deputy Grading | 10/9/2024 | Approved | MANUEL TEJADA |
| Bottom/Toe | 10/11/2024 | Partial Approval | MANUEL TEJADA |
| Excavation | 10/11/2024 | Partial Approval | MANUEL TEJADA |
| Excavation | 10/16/2024 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 10/18/2024 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 10/23/2024 | Partial Approval | MANUEL TEJADA |
| Approved Compaction Report | 10/29/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 10/29/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 10/30/2024 | Partial Approval | MANUEL TEJADA |
| Approved Compaction Report | 12/17/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Deputy Grading | 1/21/2025 | Approved | ALEXANDER HELFER |
| Deputy Other (see comments) | 3/7/2025 | No Access for Inspection | MANUEL TEJADA |
| Deputy Other (see comments) | 3/10/2025 | Partial Approval | MANUEL TEJADA |
| Deputy Other (see comments) | 3/12/2025 | No Access for Inspection | MANUEL TEJADA |
| Deputy Grading | 6/2/2025 | Conditional Approval | ALEXANDER HELFER |
| Deputy Other (see comments) | 7/2/2025 | Conditional Approval | ALEXANDER HELFER |
| Bottom/Toe | 7/18/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Deputy Grading | 7/21/2025 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 7/22/2025 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 7/23/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 7/24/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/5/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/6/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/11/2025 | Approved | ALEXANDER HELFER |
| Deputy Other (see comments) | 8/22/2025 | Conditional Approval | ALEXANDER HELFER |
| Sub-Drain | 4/28/2026 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 4/29/2026 | Not Ready for Inspection | CHARLES POWELL |
| Deputy Grading | 4/30/2026 | Corrections Issued | CHARLES POWELL |
| Sub-Drain | 5/1/2026 | Partial Approval | MATTHEW JENKINS |