2460 S PURDUE AVE 90064
Certificate Information: 2460 S PURDUE AVE 90064
- Application / Permit
- 23030-10000-02582
- Plan Check / Job No.
- B23LA07303
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Site Grading, excavation for basement, backfill for basement retaining walls
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/23/2026
Permit Application Status History
| Issued | 6/2/2023 | APPLICANT |
| Permit Finaled | 4/22/2026 | JOHNNY MIRANDA |
Permit Application Clearance Information
| CPC | Cleared | 5/3/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 5/3/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 5/3/2023 | ASHLEY RODARTE |
| Specific Plan | Cleared | 5/3/2023 | ASHLEY RODARTE |
| Low Impact Development (LID) | Cleared | 5/14/2023 | ANDRES COVARRUBIAS |
| Excavation more than 5-ft deep | Cleared | 6/2/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | B M R Enterprises; Lic. No.: 901546-B | 5250 LANKERSHIM BLVD STE 500 LOS ANGELES, CA 91601 |
| Engineer | Jahani,, Fereidoun; Lic. No.: C62875 | 3720 BLANCHE ST PASADENA, CA 91107 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/6/2023 | Approved | RUSSELL BONVOULOIR |
| Excavation | 6/14/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 8/2/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 8/2/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 8/2/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 8/8/2023 | Corrections Issued | MATTHEW JENKINS |
| Bottom/Toe | 9/8/2023 | Partial Inspection | AL GAMBLE |
| Final | 9/8/2023 | Partial Inspection | AL GAMBLE |
| Rough | 9/8/2023 | Partial Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 10/16/2023 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 11/26/2025 | Approved | JOHNNY MIRANDA |
| Bottom/Toe | 4/22/2026 | Approved | JOHNNY MIRANDA |
| Final | 4/22/2026 | Permit Finaled | JOHNNY MIRANDA |
| Rough | 4/22/2026 | Approved | JOHNNY MIRANDA |