2301 W BEVERLY BLVD 90057
Certificate Information: 2301 W BEVERLY BLVD 90057
- Application / Permit
- 23030-10000-01904
- Plan Check / Job No.
- B23LA03778
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- eplan*** SHORING FOR NEW SITE RETAINING WALL
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- Permit Finaled on 9/19/2024
Permit Application Status History
| Submitted | 3/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | SINA KHOSRAVI |
| Corrections Issued | 3/24/2023 | SINA KHOSRAVI |
| Quality Review Completed | 4/3/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/2/2023 | SINA KHOSRAVI |
| Plan Check Approved | 6/23/2023 | SINA KHOSRAVI |
| Issued | 7/7/2023 | APPLICANT |
| Permit Finaled | 9/18/2024 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/6/2023 | SINA KHOSRAVI |
Contact Information
| Architect | Fry,, Jimmy D; Lic. No.: NA26710 | , |
| Contractor | Blackwell Development Inc; Lic. No.: 1070521-B | , |
| Engineer | Baroonian,, Armen; Lic. No.: NA4227 | , |
| Engineer | Chapman,, Randy; Lic. No.: C69614 | 1407 SPYGLASS WAY CAMARILLO, CA 93012 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/19/2023 | Approved | RUSSELL BONVOULOIR |
| Excavation | 8/7/2023 | Corrections Issued | JONATHAN HOM |
| Deputy Grading | 8/8/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 8/9/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 8/10/2023 | Approved | ROBERT HUGHES |
| Deputy Grading | 8/11/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 4/30/2024 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 4/30/2024 | Approved | ALEXANDER HELFER |
| Sub-Drain | 4/30/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Bottom/Toe | 9/18/2024 | Approved | RUSSELL BONVOULOIR |
| Final | 9/18/2024 | Permit Finaled | RUSSELL BONVOULOIR |