16221 W MULHOLLAND DR 90049

Certificate Information: 16221 W MULHOLLAND DR 90049

Application / Permit
23030-10000-01870
Plan Check / Job No.
B23LA03864
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
Site Grading
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
Permit Finaled on 10/3/2024

Permit Application Status History

Submitted 3/8/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 VU NGUYEN
Corrections Issued 3/23/2023 VU NGUYEN
Quality Review Completed 3/29/2023 EUGENE BARBEAU
Applicant returned to address corrections 5/11/2023 VU NGUYEN
Applicant returned to address corrections 7/18/2023 VU NGUYEN
Applicant returned to address corrections 8/11/2023 VU NGUYEN
Applicant returned to address corrections 11/16/2023 VU NGUYEN
Plan Check Approved 3/29/2024 VU NGUYEN
Issued 4/17/2024 APPLICANT
Permit Finaled 10/2/2024 MANUEL TEJADA

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/19/2023 MARTIN FRAGOSO
Miscellaneous Cleared 3/26/2024 MAYELA VILLA
Miscellaneous Cleared 3/26/2024 MAYELA VILLA
Miscellaneous Cleared 3/26/2024 MAYELA VILLA
Miscellaneous Cleared 3/26/2024 MAYELA VILLA
Specific Plan Cleared 3/26/2024 MAYELA VILLA
ZA Case Cleared 3/26/2024 MAYELA VILLA
ZA Case Cleared 3/26/2024 MAYELA VILLA
GPI Written Notices Cleared 3/29/2024 VU NGUYEN
Grading Pre-Inspection Cleared 3/29/2024 VU NGUYEN

Contact Information

Contractor Grush Ed General Contractor Inc; Lic. No.: 246399-B 3236 EAST WILLOW STREET      SIGNAL HILL, CA 90755
Engineer Di, Bias, Craig; Lic. No.: C75205 1915 W ORANGEWOOD AVE   STE 101    ORANGE, CA 92868
Geologist Luna,, Anthony; Lic. No.: EG2777 5501 RALSTON ST UNIT 202      VENTURA, CA 93003

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drainage Devices/Catch Basin 7/1/2024 Partial Approval CHARLES POWELL
Bottom/Toe 7/23/2024 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 8/7/2024 Partial Approval MANUEL TEJADA
Bottom/Toe 8/26/2024 Approved MANUEL TEJADA
Drainage Devices/Catch Basin 8/26/2024 Approved MANUEL TEJADA
Final 8/26/2024 Corrections Issued MANUEL TEJADA
Rough 8/26/2024 Approved MANUEL TEJADA
Drainage Devices/Catch Basin 8/27/2024 Approved MANUEL TEJADA
Approved Compaction Report 9/20/2024 Approved GERMAN RODRIGUEZ MENDOZA
Final 10/2/2024 Permit Finaled MANUEL TEJADA