2340 S BEACH AVE 90291

Certificate Information: 2340 S BEACH AVE 90291

Application / Permit
23030-10000-01274
Plan Check / Job No.
B23LA03476
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
ePlan - grading for ADU IN CONJUNCTION WITH: 22010 - 10000 - 03072
Permit Issued
Issued on 6/23/2023
Issuing Office
Current Status
Permit Finaled on 11/21/2024

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 KELVIN CHUONG
Corrections Issued 3/16/2023 KELVIN CHUONG
Quality Review Completed 3/17/2023 RODOLFO ARIAS
Applicant returned to address corrections 5/30/2023 KELVIN CHUONG
Plan Check Approved 6/8/2023 KELVIN CHUONG
Issued 6/23/2023 APPLICANT
Permit Finaled 11/20/2024 MATTHEW JENKINS

Permit Application Clearance Information

Specific Plan Cleared 3/16/2023 LOUIS ORTEGA
Construction near power lines Cleared 5/19/2023 WALTER RAMIREZ

Contact Information

Architect Hewitt,, George Hopper; Lic. No.: NA39492       ,
Contractor J P Builders & Development Inc; Lic. No.: 992192-B       ,

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 7/18/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 8/8/2023 Partial Inspection MATTHEW JENKINS
Excavation 8/8/2023 Partial Inspection MATTHEW JENKINS
Rough 8/14/2023 Partial Approval ROBERT PINA
Bottom/Toe 8/17/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 8/22/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 8/28/2023 Partial Approval MATTHEW JENKINS
Deputy Other (see comments) 8/28/2023 Conditional Approval MATTHEW JENKINS
Rough 8/30/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 9/5/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 9/24/2024 Not Ready for Inspection MATTHEW JENKINS
Final 9/24/2024 Not Ready for Inspection MATTHEW JENKINS
Rough 9/24/2024 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 10/21/2024 Not Ready for Inspection MATTHEW JENKINS
Final 10/21/2024 Not Ready for Inspection MATTHEW JENKINS
Rough 10/21/2024 Not Ready for Inspection MATTHEW JENKINS
Approved Compaction Report 11/19/2024 Approved MATTHEW JENKINS
Bottom/Toe 11/20/2024 Approved MATTHEW JENKINS
Final 11/20/2024 Permit Finaled MATTHEW JENKINS
Rough 11/20/2024 Approved MATTHEW JENKINS