800 W 85TH ST 90044

Certificate Information: 800 W 85TH ST 90044

Application / Permit
23030-10000-01099
Plan Check / Job No.
B22LA25795
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading/remove and recompact for a new apt building under 22010-10000-06311
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
Permit Finaled on 5/5/2026

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 KESETE HAREGOT
Corrections Issued 1/11/2023 KESETE HAREGOT
Quality Review Completed 1/13/2023 RODOLFO ARIAS
Applicant returned to address corrections 3/9/2023 KESETE HAREGOT
Applicant returned to address corrections 3/21/2023 KESETE HAREGOT
Applicant returned to address corrections 5/8/2023 KESETE HAREGOT
Applicant returned to address corrections 5/9/2023 KESETE HAREGOT
Applicant returned to address corrections 5/17/2023 KESETE HAREGOT
Plan Check Approved 5/26/2023 KESETE HAREGOT
Plan Check Approved 6/20/2023 KESETE HAREGOT
Issued 6/21/2023 APPLICANT
Permit Finaled 5/5/2026 MICHAEL TEMPLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/2/2023 KATHERINE MENDOZA
Excavation more than 5-ft deep Cleared 5/17/2023 CALOSHA APPROVED
Low Impact Development (LID) Cleared 5/22/2023 ORVAL HERNANDEZ-MARCI
Work Adjacent to Public Way Cleared 5/23/2023 JOSE RODRIGUEZ

Contact Information

Contractor N P Construction Company; Lic. No.: 977919-B 9 CUSHING SUITE 200      IRVINE, CA 92618
Engineer Luong,, John Tuan; Lic. No.: C65214 8171 INGRAM CIR      WESTMINSTER, CA 92683
Engineer Rogers,, Robert S; Lic. No.: L8348 1124 W ANGELENO AVE   APT M    BURBANK, CA 91506
Engineer Zen,, Petrina; Lic. No.: GE3217 905 PIEDMONT      IRVINE, CA 92620
Landscape Architect Lir,, Yael; Lic. No.: LA3171 1010 SYCAMORE AVE STE 313      S PASADENA, CA 91030

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/19/2023 Partial Approval JONATHAN HOM
Deputy Grading 7/20/2023 Approved JONATHAN HOM
Bottom/Toe 7/24/2023 Partial Approval JONATHAN HOM
Deputy Grading 7/25/2023 Approved JONATHAN HOM
Bottom/Toe 7/26/2023 Not Ready for Inspection RUSSELL BONVOULOIR
Deputy Grading 7/26/2023 Approved JONATHAN HOM
Deputy Grading 7/27/2023 Approved JONATHAN HOM
Excavation 7/27/2023 Conditional Approval JONATHAN HOM
Deputy Grading 7/28/2023 Conditional Approval RUSSELL BONVOULOIR
Approved Compaction Report 8/22/2023 Approved RUSSELL BONVOULOIR
Bottom/Toe 8/30/2023 Partial Inspection JONATHAN HOM
Rough 8/30/2023 Partial Inspection JONATHAN HOM
Drainage Devices/Catch Basin 5/13/2025 Conditional Approval JONATHAN HOM
Approved Compaction Report 8/29/2025 Approved RUSSELL BONVOULOIR
Bottom/Toe 10/29/2025 Approved JONATHAN HOM
Final 10/29/2025 Partial Inspection JONATHAN HOM
Rough 10/29/2025 Approved JONATHAN HOM
Final 11/7/2025 Not Ready for Inspection MICHAEL TEMPLE
Final 4/30/2026 Corrections Issued AL GAMBLE
Final 5/5/2026 Permit Finaled MICHAEL TEMPLE