522 N CHAPALA DR 90272

Certificate Information: 522 N CHAPALA DR 90272

Application / Permit
23030-10000-00725
Plan Check / Job No.
B22LA26397
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING. 1552 CY CUT AND FILL
Permit Issued
Issued on 8/17/2023
Issuing Office
Current Status
Issued on 8/17/2023

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 NGHI SU
Corrections Issued 2/4/2023 NGHI SU
Quality Review Completed 2/24/2023 FARUK SEZER
Applicant returned to address corrections 3/28/2023 NGHI SU
Applicant returned to address corrections 7/28/2023 NGHI SU
Plan Check Approved 8/11/2023 NGHI SU
Issued 8/17/2023 APPLICANT

Permit Application Clearance Information

ZI Cleared 4/22/2023 NATHAN ROMINE
Roof/Waste drainage to street Cleared 4/25/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/2/2023 ANTHONY MAINEZ
Stormwater Pollution Mitigatn Cleared 7/14/2023 ORVAL HERNANDEZ-MARCI
Grading Pre-Inspection Cleared 7/28/2023 NGHI SU
Excavation more than 5-ft deep Cleared 8/8/2023 CALOSHA APPROVED

Contact Information

Contractor Grossman Construction & Development Inc; Lic. No.: 1052191-B       ,
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1185 HERITAGE FARM RD      HICKORY, NC 28601
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Engineer Yamashita,, Mark Alan; Lic. No.: L7155 6718 BIANCA AVE      LAKE BALBOA, CA 91406
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 24736 CALVERT STREET      WOODLAND HILLS, CA 91367
Landscape Architect Biesecker,, Craig Roy; Lic. No.: LA6522 520 S CORONADO ST APT B      LOS ANGELES, CA 90057

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/21/2023 Partial Approval JOHNNY MIRANDA
Bottom/Toe 8/23/2023 Approved VASIL MIHALEV
Excavation 8/24/2023 Partial Approval JOHNNY MIRANDA
Excavation 9/7/2023 Partial Approval JOHNNY MIRANDA
Initial Grading 9/7/2023 Partial Approval JOHNNY MIRANDA
Sub-Drain 11/30/2023 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 6/3/2024 Approved MATTHEW JENKINS