217 E VERNON AVE 90011

Certificate Information: 217 E VERNON AVE 90011

Application / Permit
23030-10000-00546
Plan Check / Job No.
B22LA04099
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading for removal and recompaction for new apartment under 22010-10000-01111.
Permit Issued
Issued on 11/2/2023
Issuing Office
Current Status
Issued on 11/2/2023

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 MANUEL MONTUFAR
Corrections Issued 3/30/2022 MANUEL MONTUFAR
Quality Review Completed 4/1/2022 EUGENE BARBEAU
Applicant returned to address corrections 8/31/2022 MANUEL MONTUFAR
Applicant returned to address corrections 9/16/2022 MANUEL MONTUFAR
Applicant returned to address corrections 9/28/2022 MANUEL MONTUFAR
Applicant returned to address corrections 8/24/2023 MANUEL MONTUFAR
Plan Check Approved 8/28/2023 MANUEL MONTUFAR
Issued 11/2/2023 APPLICANT

Permit Application Clearance Information

Stormwater Pollution Mitigatn Cleared 7/18/2023 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Parvini,, Mehdi; Lic. No.: C63186 1226 SOUZA DRIVE      EL DORADO HILLS, CA 95762
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 12/18/2023 Corrections Issued JONATHAN HOM
Initial Grading 12/22/2023 Partial Approval JONATHAN HOM
Excavation 12/29/2023 Not Ready for Inspection RUSSELL BONVOULOIR
Deputy Grading 1/3/2024 Conditional Approval RUSSELL BONVOULOIR
Excavation 1/4/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Grading 1/5/2024 Approved JONATHAN HOM
Bottom/Toe 1/9/2024 Partial Approval JONATHAN HOM
Bottom/Toe 1/11/2024 Partial Approval JONATHAN HOM
Fill/Backfill 1/11/2024 Partial Inspection JONATHAN HOM
Approved Compaction Report 4/26/2024 Approved JONATHAN HOM
Bottom/Toe 5/1/2024 Partial Inspection JONATHAN HOM
Final 5/1/2024 Partial Inspection JONATHAN HOM
Rough 5/1/2024 Partial Inspection JONATHAN HOM
Bottom/Toe 4/11/2025 No Access for Inspection JONATHAN HOM
Initial Grading 11/24/2025 Not Ready for Inspection JONATHAN HOM
Excavation 11/25/2025 Partial Approval AL GAMBLE
Bottom/Toe 12/2/2025 Partial Approval AL GAMBLE
Excavation 12/2/2025 Partial Approval AL GAMBLE
Approved Compaction Report 2/20/2026 Approved AL GAMBLE