1059 S HOLT AVE 90035

Certificate Information: 1059 S HOLT AVE 90035

Application / Permit
23030-10000-00466
Plan Check / Job No.
B23LA01231
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING PERMIT FOR NEW APARTMENT, BACKFILL ALONG PERIMETER BASEMENT WALLS.
Permit Issued
Issued on 11/6/2024
Issuing Office
Current Status
Issued on 11/6/2024

Permit Application Status History

Submitted 1/25/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 VU NGUYEN
Corrections Issued 2/22/2023 VU NGUYEN
Quality Review Completed 2/22/2023 EUGENE BARBEAU
Plan Check Approved 11/5/2024 VU NGUYEN
Issued 11/6/2024 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 3/24/2023 ANACANY HURTADO
CPC Cleared 3/24/2023 ANACANY HURTADO
Miscellaneous Cleared 3/24/2023 ANACANY HURTADO
Miscellaneous Cleared 3/24/2023 ANACANY HURTADO
Stormwater Pollution Mitigatn Cleared 10/31/2024 LUIS LUVANO
Excavation more than 5-ft deep Cleared 11/4/2024 CALOSHA APPROVED

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: NA37588       ,
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Salehipour,, Sassan A; Lic. No.: C44172 1290 NORTH LAKE AVENUE STE 204      PASADENA, CA 91104

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 11/8/2024 Partial Inspection JONATHAN HOM
Drainage Devices/Catch Basin 11/19/2024 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 12/4/2024 Partial Approval JONATHAN HOM
Initial Grading 12/18/2024 Partial Inspection JONATHAN HOM
Sub-Drain 12/18/2024 Conditional Approval JONATHAN HOM
Initial Grading 1/2/2025 Partial Approval JONATHAN HOM
Initial Grading 1/15/2025 Not Ready for Inspection JONATHAN HOM
Sub-Drain 4/17/2025 Partial Approval JONATHAN HOM