1750 S NAVY WAY 90731

Certificate Information: 1750 S NAVY WAY 90731

Application / Permit
23030-10000-00239
Plan Check / Job No.
B22LA26293
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
EPLAN PROPOSED GRADING FOR PROPOSED TRAINING BUILDING. 2 OF 3
Permit Issued
Issued on 3/17/2023
Issuing Office
Current Status
Permit Finaled on 7/18/2024

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 MICHAEL LOPEZ
Corrections Issued 1/24/2023 MICHAEL LOPEZ
Quality Review Completed 2/6/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/6/2023 MICHAEL LOPEZ
Applicant returned to address corrections 3/14/2023 MICHAEL LOPEZ
Plan Check Approved 3/16/2023 MICHAEL LOPEZ
Issued 3/17/2023 APPLICANT
Permit Finaled 7/17/2024 MATTHEW JENKINS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mason Building And Design Llc; Lic. No.: 1042113-B 149 PARKSHORE DR      FOLSOM, CA 95630
Engineer Khamsi,, Ali; Lic. No.: C74768 124 VIA UNDINE      NEWPORT BEACH, CA 92663

Inspector Information

JESUS RODRIGUEZ, (213) 216-1187 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/24/2023 Partial Inspection AL GAMBLE
Initial Grading 4/17/2023 Approved JONATHAN HOM
Bottom/Toe 4/19/2023 Partial Approval MATTHEW JENKINS
Deputy Grading 4/19/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 4/20/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 4/21/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 4/24/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 4/25/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 4/26/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 6/13/2023 Approved AL GAMBLE
Drainage Devices/Catch Basin 6/13/2023 Not Ready for Inspection AL GAMBLE
Excavation 6/13/2023 Partial Approval AL GAMBLE
Deputy Grading 6/27/2023 Conditional Approval MATTHEW JENKINS
Approved Compaction Report 7/3/2023 Partial Inspection AL GAMBLE
Approved Compaction Report 7/20/2023 Partial Inspection AL GAMBLE
Deputy Grading 8/7/2023 Approved AL GAMBLE
Deputy Grading 8/9/2023 No Access for Inspection AL GAMBLE
Deputy Grading 8/18/2023 Conditional Approval AL GAMBLE
Deputy Grading 9/8/2023 Approved AL GAMBLE
Bottom/Toe 10/5/2023 Partial Approval AL GAMBLE
Deputy Grading 10/5/2023 Partial Approval AL GAMBLE
Deputy Grading 10/17/2023 Conditional Approval AL GAMBLE
Deputy Grading 10/18/2023 Approved AL GAMBLE
Deputy Grading 10/19/2023 Approved AL GAMBLE
Bottom/Toe 10/20/2023 Partial Inspection MATTHEW JENKINS
Deputy Grading 10/20/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 10/24/2023 Approved AL GAMBLE
Deputy Grading 10/25/2023 Conditional Approval AL GAMBLE
Deputy Grading 11/3/2023 Approved AL GAMBLE
Deputy Grading 11/17/2023 Partial Approval AL GAMBLE
Deputy Grading 11/21/2023 No Access for Inspection AL GAMBLE
Deputy Grading 12/1/2023 Approved AL GAMBLE
Deputy Grading 12/4/2023 Approved AL GAMBLE
Deputy Grading 12/6/2023 Approved AL GAMBLE
Deputy Grading 12/6/2023 Partial Approval AL GAMBLE
Deputy Grading 12/8/2023 Approved AL GAMBLE
Deputy Grading 12/13/2023 Approved AL GAMBLE
Deputy Grading 12/15/2023 Approved AL GAMBLE
Deputy Grading 1/5/2024 Approved AL GAMBLE
Deputy Grading 1/10/2024 Approved AL GAMBLE
Deputy Grading 1/16/2024 Approved AL GAMBLE
Deputy Other (see comments) 1/17/2024 Approved AL GAMBLE
Deputy Other (see comments) 1/26/2024 Approved AL GAMBLE
Deputy Grading 1/29/2024 Approved AL GAMBLE
Deputy Grading 2/13/2024 No Access for Inspection VASIL MIHALEV
Deputy Grading 2/14/2024 No Access for Inspection VASIL MIHALEV
Initial Grading 2/14/2024 Partial Inspection AL GAMBLE
Deputy Grading 2/15/2024 Partial Approval AL GAMBLE
Deputy Grading 2/16/2024 Approved AL GAMBLE
Deputy Grading 2/22/2024 Approved AL GAMBLE
Deputy Other (see comments) 4/24/2024 Conditional Approval AL GAMBLE
Approved Compaction Report 6/25/2024 Approved VASIL MIHALEV
Bottom/Toe 7/1/2024 Not Ready for Inspection MATTHEW JENKINS
Final 7/1/2024 Not Ready for Inspection MATTHEW JENKINS
Rough 7/1/2024 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 7/5/2024 Partial Inspection MATTHEW JENKINS
Final 7/5/2024 Corrections Issued MATTHEW JENKINS
Rough 7/5/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 7/17/2024 Approved MATTHEW JENKINS
Final 7/17/2024 Permit Finaled MATTHEW JENKINS
Rough 7/17/2024 Approved MATTHEW JENKINS