1312 N MARIPOSA AVE 90027
Certificate Information: 1312 N MARIPOSA AVE 90027
- Application / Permit
- 23030-10000-00131
- Plan Check / Job No.
- B22LA25474
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR REMOVE AND RECOMPACT FOR NEW DUPLEX (3' DEEP, 3' AWAY); EXCAVATION AND BACKFILL FOR NEW RETAINING WALL
- Permit Issued
- Issued on 8/28/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/25/2025
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/9/2023 | SELLA BENYAMIN |
| Quality Review Completed | 1/20/2023 | STEVEN KIM |
| Plan Check Approved | 3/2/2023 | SELLA BENYAMIN |
| No Progress | 5/30/2023 | SELLA BENYAMIN |
| Plan Check Approved | 5/30/2023 | SELLA BENYAMIN |
| No Progress | 6/6/2023 | SELLA BENYAMIN |
| Plan Check Approved | 6/6/2023 | SELLA BENYAMIN |
| Issued | 8/28/2023 | APPLICANT |
| Permit Finaled | 3/24/2025 | ALEXANDER HELFER |
Permit Application Clearance Information
| Hold | Cleared | 10/4/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Tre Development Llc; Lic. No.: 1075573-B | , |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
Inspector Information
| LANNY MERRICK, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 10/10/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 10/17/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 10/24/2023 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 10/26/2023 | Approved | ALEXANDER HELFER |
| Initial Grading | 10/30/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 11/13/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Initial Grading | 12/19/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 1/8/2024 | Approved | RUSSELL BONVOULOIR |
| Bottom/Toe | 1/18/2024 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 3/21/2024 | Approved | LANNY MERRICK |
| Bottom/Toe | 3/24/2025 | Approved | ALEXANDER HELFER |
| Final | 3/24/2025 | Permit Finaled | ALEXANDER HELFER |
| Rough | 3/24/2025 | Approved | ALEXANDER HELFER |