2092 N MOUND ST 90068

Certificate Information: 2092 N MOUND ST 90068

Application / Permit
23026-30000-00129
Plan Check / Job No.
B23WL02002
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(2) New retaining walls
Permit Issued
Issued on 5/15/2025
Issuing Office
West Los Angeles
Current Status
Issued on 5/15/2025

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 REZA HAGHIGHAT
Corrections Issued 8/13/2023 REZA HAGHIGHAT
Building Plans Picked Up 8/18/2023 APPLICANT
Quality Review Completed 8/20/2023 KAVIAN REFAHI
Plan Check Approved 12/9/2024 REZA HAGHIGHAT
Issued 5/15/2025 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 9/27/2023 DANIEL CORONADO
Landscape for retaining wall Cleared 11/28/2023 DALIA MOKAYED
Excavation more than 5-ft deep Cleared 12/9/2024 CALOSHA APPROVED
Grading Pre-Inspection Cleared 12/9/2024 REZA HAGHIGHAT

Contact Information

Contractor Pomer Construction Inc; Lic. No.: 908354-B 2355 WESTOOD BLVD STE 385      LOS ANGELES, CA 90064
Engineer Miscione,, Frank Vincent; Lic. No.: C69031 30014 LEXINGTON      VAL VERDE, CA 91384
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 10/6/2025 Conditional Approval CRAIG VAUGHAN
Deputy Grading 10/7/2025 Conditional Approval CRAIG VAUGHAN
Deputy Grading 10/8/2025 Conditional Approval BRIAN SULLIVAN
Deputy Grading 10/9/2025 Conditional Approval CRAIG VAUGHAN
Deputy Grading 10/10/2025 Conditional Approval CRAIG VAUGHAN
Piling/Pier/Caisson 11/4/2025 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 11/10/2025 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 12/1/2025 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 12/3/2025 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 12/4/2025 Conditional Approval RAMAZANALI ALMASI
Deputy Shotcrete 12/19/2025 Approved ROBERT PINA
Footing/Foundation/Slab 12/19/2025 Approved ROBERT PINA
Deputy Other (see comments) 12/22/2025 Approved ROBERT PINA
Deputy Shotcrete 12/22/2025 Approved ROBERT PINA
Footing/Foundation/Slab 3/11/2026 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/12/2026 Approved ROBERT PINA
Deputy Reinf. Concrete 3/13/2026 Approved ROBERT PINA
Deputy Shotcrete 3/31/2026 Conditional Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 4/6/2026 Partial Approval RAMAZANALI ALMASI
Deputy Shotcrete 4/10/2026 Conditional Approval RAMAZANALI ALMASI
Deputy Shotcrete 4/13/2026 Approved ROBERT PINA
Deputy Reinf. Concrete 4/15/2026 Conditional Approval RAMAZANALI ALMASI
Grading Pre-Inspection 4/29/2026 Conditional Approval JONATHAN HOM