1834 N WESTERLY TER 90026
Certificate Information: 1834 N WESTERLY TER 90026
- Application / Permit
- 23020-30000-01098
- Plan Check / Job No.
- B23WL01416
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- CONVERT GARDEN WALL TO RETAINING WALL DUE TO LOWER POOL/SPA PER 3 SOILS REPORTS AND CALCS IN HILLSIDE ORD. AREA ---2 OF 2---
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/19/2025
Permit Application Status History
| Submitted | 5/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2023 | YASHAR EMAMI |
| Plans on Hold | 6/6/2023 | YASHAR EMAMI |
| Hold Released | 6/30/2023 | SUNMIN LEE |
| Corrections Issued | 6/30/2023 | SUNMIN LEE |
| Building Plans Picked Up | 7/6/2023 | APPLICANT |
| Quality Review Completed | 7/12/2023 | JOHN FRANCIA |
| Applicant returned to address corrections | 7/31/2023 | SUNMIN LEE |
| Plan Check Approved | 4/16/2024 | SUNMIN LEE |
| Issued | 4/22/2024 | APPLICANT |
| Permit Finaled | 8/18/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 7/19/2023 | SPENCER WEJROWSKI |
| Landscape for retaining wall | Cleared | 7/19/2023 | SPENCER WEJROWSKI |
| Excavation more than 5-ft deep | Cleared | 4/16/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 4/16/2024 | SUNMIN LEE |
Contact Information
| Contractor | Caire John Construction Inc; Lic. No.: 626684-B | 2028 LOMBARDY DR LA CANADA, CA 91011 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/20/2025 | Not Ready for Inspection | LANNY MERRICK |
| Final | 3/26/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Reinforced Concrete Frame | 6/12/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 8/18/2025 | Permit Finaled | RUSSELL BONVOULOIR |